STT 110 / STT 160

7.2. Assembly

»

Please ensure adequate carrying capacity of the lifting equipment.

Check the carrying capacity of the point of installation, particularly if installed on a platform.

The place selected for installation should be as free of vibrations as possible.

The main switch must be freely accessible.

Ground the equipment against electrostatic charging.

F

The machine must not be tilted or laid on its side.

Because of its compact construction the dryer can be installed directly beside the processing ma- chine (drying hopper on the processing machine) or with one or more drying hoppers as a mov- able facility (compact facility).

Special foundations are not necessary for installation.

The dryer must be installed on a level surface and must not be exposed to excessive humidity. The maximum permissible ambient temperature is 45 °C (113°F).

To facilitate servicing, the dryer should be installed in such a way that that it is accessible from 3 sides. Make sure that the air filters can be changed without problems.

To conserve energy, keep the distance between dryer, hopper and processing machine as small as possible.

The wheels of the compact unit should be locked to ensure stable installation.

The foil should be removed from the drying hopper.

7.3. Storage

The control system may only be stored at temperatures from 0 to +55°C (32 to +131 °F).

Between delivery and machine commissioning the equipment should be stored in a dry, dust-free and vibration-free room.

SM2-605

Transport, Assembly and Storage 7-3