INSTALLATION INSTRUCTIONS

COMMISSIONING

6.COMMISSIONING

6.1Close all windows and doors to the room, check all controls, and allow fire to burn on maximum for 5 minutes. Test for spillage of flue products using a smoke match. Pass the lighted smoke match along the top front edge just inside the opening or canopy. See diagram 34.

34

6.2If the fire spills, run for a further 10 minutes and re-check. If there is still spillage, disconnect the fire and seek expert advice

6.3If there are extractor fans in the room or adjacent rooms, the spillage test must be repeated with the extractors running on maximum.

6.4The burner pressure on this appliance is pre-set, provided the correct inlet pressure is obtained at the test point on the inlet connection, with the appliance on full, the appliance will work correctly. Carrying out a gas rate test will check the correct operation.

( The test points on the gas valve are not used on this appliance.)