23
Model C713 Operating Procedures
Step 5
Insert the beater drive shaft through the r ear shell
bearing in the freezing cylinder and engage the hex
end firmly into the drive coupling.
Figure 32
USE EXTREME CAUTION when handling
the beater assembly. The scraper blades are very
sharp and may cause injury.
Step 6
Before installing the beater assembly,check the
scraper blades. If they are in good condition, take
one of the scraper blades and slip it under the hook
at the front of the beater. Wrap the blade ar ound the
beater, following the helix and pushing the blade
down onto the helix as you wrap. At the back end of
the beater, slip the blade under the hook.
Figure 33
Repeat this step for the second scraper blade.
Step 7
Holding the beater securely, slide the beater into the
freezing cylinder about one-third of the way in.
Looking into the freezing cylinder, align the hole at
the rear of the beater with the flats on the end of t he
drive shaft.
Figure 34
Step 8
Slide the beater the remainder of the way into the
freezing cylinder and over the end of the drive shaft.
The beater should fit snugly but not so tightly t hat
the beater cannot be turned slightly to engage the
drive shaft.
Make sure the beater assembly is in position over
the drive shaft. Turn the beater slightly t o be certain
that the beater is properly seated. When in position,
the beater will not protrude beyond the front of the
freezing cylinder.
Step 9
Repeat these steps for the other sid e of the
machine.
Step 10
To assemble the freezer door, place the door
gaskets into the grooves on the back of the freez er
door. Slide the front bearings over the baffle rods.
The flanged edges should be against the door. DO
NOT lubricate the gaskets or bearings.