PRE-ENERGIZATION CHECK

Page 18

PRE-ENERGIZATION CHECK

GENERAL

BEFORE ENERGIZING THE CIRCUIT BREAKER for the first time, follow the procedure below to verify that the equipment is properly installed and functional.

ELECTRICAL CHECKS

Electrical shock hazard. WARNING Do not touch energized

components during a test using auxiliary power.

GENERALELECTRICAL CHECKSDANGER

Hazardous Voltage. Turn off and lock out all primary and control circuit power sources prior to performing this pre-energization check.

An electrical insulation resistance test should be performed to verify that the circuit breaker and associated field wiring are free from short circuits and grounds. Refer to the MAINTENANCE Section of this manual for additional information.

components during a test using auxiliary power.Do not remove, cover or destroy any safety signs.WARNING

Manual backgroundManual backgroundWARNING

Do not operate this equipment until a complete safety inspection has been made.

Do not energize damaged equipment that has not been repaired or verified.

Manual backgroundManual backgroundWARNING

Hazardous voltages are present during dielectric testing which can result in serious injury or death. High potential tests should be performed only by qualified personnel.

Manual backgroundManual backgroundWARNING

Manual backgroundManual backgroundWARNING

Do not remove, cover or destroy any safety signs.

Do not operate this equipment until all panels and covers have been installed.

The circuit breaker must be set to the OFF position before energizing incoming power.

All blocks or other temporary braces used for shipment must be removed.

Before closing the enclosure, all metal chips, scrap wire and other debris left over from installation must be cleaned out.

Cover all unused openings. Install all panels, guards and covers.

A supply of spare parts should be established.

Instruction manuals and diagrams should be collected and filed.