INSTALLATION (continued)
press this button
Florham Park NJ 07932 USA
TRANSFER SWITCH TEST | BYPASS TIME DELAY SET ENGINE EXERCISER |
Press for 15 Seconds | Press until light FLASHES |
observe these lights
Figure
3 – Electrical Operation
First check nameplate on transfer switch; rated voltage must be the same as normal and emergency line voltages.
!
Verify that the feeders have been connected to the proper lugs.
Use extreme caution when using a meter to measure voltages in the following steps. Do not touch power terminals; shock, burns, or death could result !
Perform steps 1 through 8 at the right. Observe the status lights. See Figure
●Black circle means light is on. ❍ White circle means light is off.
NOTE: If Motor Load Transfer feature is activated, then transfer may not occur immediately after the respective time delays. Transfer will only occur when the phase relationship between sources is correct.
This completes the Functional Test of the ASCO Series 300 Automatic Transfer Switch. Leave the
The normal source must be |
|
available and the generator |
|
1 must be ready to start. |
|
Check that the Normal Source |
|
Available light is on. |
|
Press and hold the Transfer | TRANSFER SWITCH TEST |
2Switch Test button until the engine starts and runs. This should happen within 15 sec.
3The Emergency Source Available light should come on.
The transfer switch should transfer to the Emergency
4position. The Load Connected to Emergency light should come
on and the Load Connected to Normal light should go off.
If the transfer to emergency |
|
delay is used the transfer | BYPASS TIME DELAY |
5should occurs after a time delay (up to 5 minutes).
For immediate transfer press the Bypass Time Delay button.
The transfer switch should transfer back to the Normal
6position. The Load Connected to Normal light should come on
and the Load Connected to Emergency light should go off.
If the retransfer to normal delay |
|
is used the retransfer should | BYPASS TIME DELAY |
7occur after a time delay (up to 30 minutes).
For immediate retransfer press the Bypass Time Delay button.
The unloaded running delay keeps the generator running for
85 minutes