Framing

CR Series Woodburning Fireplaces

Framing

Framing can be constructed before or after the fire- place is set in place, however, most installers build the frame before setting the fireplace.

Frame fireplace with 2 x 4 lumber or heavier materi- als. Refer to framing dimensions in Figures 1 or 2 for basic fireplace specifications. Headers and support studs must be turned on end as illustrated in Figure 2, Page 4.

NOTE: Framing should be positioned to accommo- date wall covering and fireplace facing material.

Hard, Flat

Surface

Insulation

Platform

FP555CR

Fig. 7 Insulation between platform and fireplace.

Chimney Set-up

Since you have already preplanned the chimney run, you should know exactly how the installation is to be accomplished — how much pipe is required, the number of elbows, if any, and type of termination to be used.

CAUTION: REPORT TO YOUR DEALER ANY PARTS DAMAGED IN SHIPMENT, SPECIFICALLY CHECK THE END CONNECTION OF CHIMNEY

SECTIONS AND ELBOWS.

Straight-Up Chimney Installation

To locate the centerline of the flue put the fireplace in final position and place a plumb bob from the ceiling to the center of the fireplace flue collar. Mark this spot on the ceiling. Draw a line through that mark to either side of the firebox and indicate dimension X to locate the side wall framing. (Fig. 8) Be sure to observe clear-

8

ance requirements for side and parallel combustible walls as noted in Figure 20, Page 15.

Offset Installation

In order to clear an obstruction, it may be necessary to offset chimney from vertical. This is accomplished by using CFM Corporation elbows. Use the 30° Offset Elbow table on Page 5 to determine proper offset and parts required.

Each offset requires two (2) elbows. The second elbow is equipped with support straps. It is very important to install the second elbow in each offset as close to the ceiling or support as possible so the elbow straps can be secured to framing members to help support the weight of the chimney.

Determine offset distance of your chimney arrange- ment from centerline of fireplace to centerline of chim- ney where it is to pass through ceiling.

Locate center point of the chimney on ceiling as though a straight up chimney arrangement is to be used. Measure your offset dimension from the chim- ney center point on the ceiling.

 

Chimney Centerline

Actual Centerpoint

 

10³⁄₈

 

(264mm)

 

Plumb Line

 

Plumb Bob

 

Imaginary Center-

 

point

 

FP556CR

Fig. 8

Locate centerline of chimney with plumb line.

 

20001316

Page 8
Image 8
Vermont Casting CR36R, CR36L manual Framing, Chimney Set-up, Straight-UpChimney Installation, Offset Installation, 20001316