Wayne-Dalton 2411, 2415 warranty Refer To Strutting Schedule Insert

Models: 2411 2415

1 16
Download 16 pages 21.33 Kb
Page 6
Image 6
Refer To Strutting Schedule Insert.

NOTE: SUPPORT BRACKETS

ARE SUPPLIED ON ALL DOORS

REQUIRING DOUBLE END

STILES

An Extra Support Bracket

Will Need To Be Added To

Top Brackets On Double

Endstile Applications

Top bracket installation illustration.

Secure each bracket using (2) 1/4” X 7/8” self-tapping screws. Doors over 16’2” wide or doors over 8 sections high require double top brackets.

Refer To Strutting Schedule Insert.

Secure U-bar to each center stile using (2) 1/4 - 20 X 7/8” TEK Screws

Fig. K

Secure each end of Top Section using (2) 1/4 - 20 X 7/8” TEK Screws and Strut Clips per End

Stile

3” UBar

Manual background 6” Welded Truss

Manual background Secure each end using

(2)1/4 - 20 X 7/8” TEK Screws per stile

STEP 4. Products over 12’2” require U-bars to be secured to each section. Position the 2” or 3” Ubars below the lower hinge leaf and attach with (2) 1/4-20 X 7/8” tek screws (1/2” from section edge) as shown in Fig. K.

Doors requiring trusses, position the truss below the lower hinge leaf (1/2” from the section edge) and secure truss using (2) 1/4”-20 x 7/8” self-drilling and tapping screws per stile. Refer to Fig. K.

Doors requiring (2) welded trusses or 8” truss refer to Auxiliary Installation Instructions.

STEP 5. Leveling Door. (Bottom section) Center and level (or support to a known grade level) the bottom section in the opening, as seen in Fig. L. Temporarily attach the vertical tracks to the jambs. Allow 1/2” clearance between the section and the track as illustrated in the Sideroom illustrations.

It is important that the bottom of each track is in the same level. (shim if necessary)

Products being installed to precast or block must use a 3/8 x 3” long sleeve anchor to attach the verticals to the building. Use the slots in the wall angle as a drill template, drill a 3/8” hole (3-1/2” deep) and secure to anchor.

STEP 6. Installing the Door Sections Secure the end hinges, (one side only) center hinges, and strutting

( if applicable) as previously illustrated. Locate the Lock Section (usually the second) and insert a roller into the end hinge. Stack this section into the opening by hooking the roller in the vertical track and lower onto the bottom section. Insert a roller into the appropriate end hinge and insert into vertical track on the opposite end. Secure to the section using the self-tapping screws. Align the section edges, flip up the upper hinge leafs and secure to the lock section using the self-tapping screws. Continue to hardware and stack the remaining sections in the proper sequence. Attach the top brackets to the upper corners using self drilling and tapping screws as shown in Fig. L.

NOTE : Top section maybe installed now or may wait until the last step (installer preference)

STEP 7. Installing the Vertical Track: Adjust the vertical track to 1/2” spacing from the bottom section and 3/4” at the top section (splice) Refer to page 5. Permanently secure each vertical to the jambs using the following fasteners:

Steel Jambs: 5/16” x 1” self drilling and tapping screw.

Wood Jambs: 5/16” x 1-5/8” lag screw.

Precast or Block: 3/8” x 3” sleeve anchor.

The left hand vertical track assembly indicates the standard fastener spacing.

PG. 6

Page 6
Image 6
Wayne-Dalton 2411, 2415 warranty Refer To Strutting Schedule Insert