AQUA PLUS
Boiler-side piping (continued)
Figure 8 Zoning with circulators — primary/secondary system piping
Notes
•Place circulators at begin- nings of zones. Placing them at the ends of zones could result in heating idle zones.
•Size manifold piping for total flow of all zone cir- culators.
•Locate flow / check valves as close as possible to water heater boiler side connec- tions — to reduce heat loss between cycles.
Wiring
•WMCR zone controller, optional priority — Fig- ure 18, page 21.
1.This drawing is conceptual only. It shows representa- tive piping components and layout.
2.See boiler manual for spe- cific details on installing the boiler.
Recommended flow rate and minimum
Heater | GPM | Pipe | Heater | GPM | Pipe | |
model | size | model | size | |||
|
| |||||
|
|
|
|
|
| |
35 | 8 | 1” | 85 | 14 | 1¼” * | |
|
|
|
|
|
| |
45 | 8 | 1” | 105 | 14 | 1¼” * | |
|
|
|
|
|
| |
55 | 8 | 1” | Requires 1¼”x1” reducers at water heater | |||
|
|
|
|
|
|
GV90+ or Ultra gas boilers:
DO NOT apply the drawings in this manual. Refer only to the boiler manual.
12 | Part number |