Installation
AC Wiring - Specific
The following AC connections are specific to installing the Sine Wave Plus Inverter/chargers in a
Grounding
Neutral Bonds
Inverter to AC Distribution Panel
The following steps are illustrated in Figure
To connect the AC wiring for an
1.Connect GROUND (green) wires:
a)from the primary earth/ground to the AC distribution panel,
b)from the L1 inverter AC ground bar to the inverter panel ground bar,
c)from the L2 inverter AC ground bar to the inverter panel ground bar.
2.Connect NEUTRAL (white) wires:
a)from the NEUTRAL bus in the inverter panel, to the ground bar in the inverter panel,
b)from the L1 inverter NEUTRAL OUT terminal, to the L2 inverter NEUTRAL 2 terminal.
c)from the L2 inverter NEUTRAL OUT terminal to the inverter panel NEUTRAL bus. (Common neutral bond in inverter panel).
3.Connect a HOT wire:
a)(black) from the L1 inverter AC HOT OUTPUT (120 Vac) to the inverter panel L1 terminal,
b)(red) from the L2 inverter AC HOT OUTPUT (120 Vac) to the inverter panel L2 terminal.
4.Torque all inverter terminal block connections to 25