Victoreen 875
Operators Manual
2.An auxiliary pulse from pin 3 of U208 to the automatic pulse generating circuits resets them so that an automatically generated pulse will be present 17.1 minutes later if the ECS Test is not conducted manually during that time. The purpose of this pulse is to insure continued operation of automatic testing.
5.15 Outputs of U206 Pulse Generator on the ECS Board
We have noted that U206 can be triggered by pressing the ECS button. Its main output is a power pulse to the ramp generator. However, it also initiates a pulse from U203 (pin 10) to pin 5 of U207A, the muting multivibrator. The muting multivibrator also has two outputs:
1.One output to U203 that ultimately causes a muting pulse six seconds wide at terminal 9. This is coupled to the power supply board on pin M. It also returns to the circuit so that jitters will be eliminated on manual ECS.
2.A second output to U207 is a
5.16 Operation of the Latch Circuit
The latch circuit has two inputs and one output:
Input 1 - Enters on pin 6 (U202) and pin 10 (U208), which are connected. This is the monitoring input. Its value is the result of the ECS Test. It enables the circuit to change state only after the conditions brought about by the ECS Test have stabilized.
Input 2 - Enters pin 1 (U202) and pin 5 of U202 which are connected. The output is taken from pin 10 and pin 2 of U202, which are connected.
Output - The output may be either 0 V, which is a pass indication, or +14 VDC, which is a fail indication. The two NOR gates (pins 8, 9, 10, and pins 11, 12, 13) are effectively a
Input 1 has a normal resting voltage of +15 V. However, during the ECS Test it takes on a voltage determined by the steady detector current that exists during the ECS Test. This current generates a voltage of about 2.57 V (0.33 scale) in the panel meter, at which time pin 6 of U202 is at approximately 0 V. If, at this instant, the enabling voltage (input 2) arrives, it will cause the
Input 2 is initiated by pressing the ECS button, but its actual occurrence in time is delayed so that it occurs during the flat portion of the current cycle generated by the ECS ramp.
Assume that the green light is ON at the beginning of the ECS Test. Actually this is probable because:
If the green light were off, troubleshooting would not begin with the ECS Test. With this assumption we can work backwards in the truth table (Table
In Figure
When the enable pulse arrives in the two cases of the signal pulse [pass (L) or fail (H)] the following conditions exist:
U202, pins 12, 10 L (Assumed as initial condition)