SP Switch environment (MAP 0600)
Table
Priority | Component | Action | |
|
|
|
|
1 | Fan 1, 2, 3, 4 or 5 | a. Check specified fans for blockages or loose cable | |
|
| ||
(1 of 5) |
|
| connections. |
| b. Fix any obvious problems and continue at ªStep | ||
|
| ||
|
|
| |
|
| c. If you do not find any problems, continue at Priority 2. | |
|
|
|
|
2 | Fan 1, 2, 3, 4 or 5 | a. Replace fans as described in Chapter 4, ªFRU | |
|
| ||
(2 of 5) |
|
| removals and replacementsº on page |
| b. | Continue at ªStep | |
|
| ||
|
|
|
|
3 | Switch supervisor card | a. | Replace the card. |
|
| ||
(3 of 5) |
| b. | Continue at ªStep |
|
|
| |
|
|
|
|
4 | Switch supervisor control cable | a. Replace the cable. Refer to Figure | |
|
| ||
(4 of 5) |
|
| connections. |
| b. Continue at ªStep | ||
|
| ||
|
|
| |
5 | All replaced | Call next level of support. | |
(5 of 5) |
|
|
|
|
|
|
|
Inner Chassis Cable
P4 (Power Card)
2 x 1
P5 | P3 |
(Switch SV Card) |
|
2 x 20 |
|
P6 (Power Card)
2 x 1
Front Chassis Cable
P7, P8 (CB) | P9 (LED) | ||||
|
|
|
|
|
|
|
|
|
|
|
|
P1
P2 (Fan 1) | P3 (Fan 2) | P4 (Fan 3) | P5 (Fan 4) | P6 (Fan 5) |
2 x 2 | 2 x 2 | 2 x 2 | 2 x 2 | 2 x 2 |
Figure 1-3. SP Switch inner chassis and front chassis cables
Step 0600-012
You performed the recommended action in Table
1.Component replaced or reseated.
2.Reconnect all cables inside the SP Switch.
3.Install front panel assembly and reinstall front retaining screws (see ªService position proceduresº on page
4.Connect only power (J1) and supervisor (J2) cables at the rear of the SP Switch.
5.Put the SP Switch's circuit breaker into the On (`1') position.