IBM RS/6000 SP manual Switch supervisor self-test, Verification tests using Perspectives

Page 74

The files ending in .out are produced by running the appropriate command to dump internal (in memory) trace information or dump data to a file. The completed output file will be found in /var/adm/SPlogs/css/css.snap.[date-time]tar.Z.

css.snap avoids flooding /var by following these rules:

vIf less than 10% of /var is free, css.snap exits.

vIf the CSS portion of /var is more than 30% of the total space in /var, css.snap erases old snap files until the CSS share sinks below 30%. If successful, css.snap proceeds. If not, it exits.

css.snap is called automatically from the fault-service daemon when certain serious errors are detected. It can also be issued from the command line by service personnel when a switch or adapter related problem is indicated.

Switch supervisor self-test

The following procedures will help you perform self-test on the switch supervisor cards. Upon completion of this test, return to the procedure that sent you here.

1.Power off switch assembly from the circuit breaker on the front of the unit.

2.Detach supervisor harness from connector at back of the unit. Detaching the supervisor harness removes the 12 volt power from the supervisor card.

3.Reinsert the supervisor harness to perform the supervisor card self-test.

4.Check green and yellow LEDs on front of the unit.

This self-test should indicate one of the following conditions for the processor node:

Self-test Conditions

Pass sequence

a.Both LEDs light (about 10 seconds)

b.Green LED stays lit, while yellow LED goes off (about two seconds)

c.Green LED stays lit, while yellow LED flashes node address

d.Both LEDs turn off (about two seconds)

e.Both LEDs light (about one second)

Fail conditions

vGreen and Yellow LEDs never light

vYellow LED flashes wrong address

Verification tests using Perspectives

This section gives you the basic information needed to check the supervisor cards on a single node, frame, or switch.

Node supervisor verification

From the Hardware Perspectives window:

1.The Hardware Perspective should open with a node pane displayed. If it does not, or if you would like to open an additional node pane:

a.Click the Add Paneicon on the tool bar v The Add Pane dialog box opens

b.From the Pane Typepull down, select Nodes

c.Select your choice of adding the pane to the current window or to a new window

d.If desired, enter a new pane title

e.Click OKto open the pane and close the dialog box

3-4RS/6000 SP: SP Switch Service Guide

Image 74
Contents IBM Page IBM Fifth Edition April Contents FRU removals and replacements Figures Vi RS/6000 SP SP Switch Service Guide Tables ViiViii RS/6000 SP SP Switch Service Guide Safety and environmental notices Safety noticesRS/6000 SP SP Switch Service Guide SPSFD017 Xii RS/6000 SP SP Switch Service Guide Laser safety information Environmental notices Product recycling and disposalXiv RS/6000 SP SP Switch Service Guide Related information About this bookWho should use this book How to send your comments Summary of changes Xviii RS/6000 SP SP Switch Service Guide Maintenance Analysis Procedures MAPs Switch description and problem determination MAP Flashing Power GreenEnvironment Yellow Errors in /var/adm/SPlogs/css/out.top see Priority Message or condition ActionSP Switch environment MAP Condition ActionSwitch connector resistance values Step SP Switch inner chassis and front chassis cables Priority Component ActionStep 10RS/6000 SP SP Switch Service Guide Step 12RS/6000 SP SP Switch Service Guide SP Switch power MAP SP Switch power MAP PDU-BH-P1 PDU-BH-P2 PDU-BH-P3 PDU-BH-P4 PDU-BH-P5 From From P1 pinEprimary SP Switch function MAPEstart Splstdata -n pg Pg /var/adm/SPlogs/css/out.top NotesSP Switch function MAP Splstdata -s pg Error # Message/condition Description and actionIf the cabling does not match, correct the cabling SDRGetObjects DependentNodeL03-N01 L01-S00-BH-J18E02-S00-BH-J18 E02-N04Priority Message/condition Action Var/adm/SPlogs/css/out.top file haveStep Service Request Number Failing components DescriptionSRN 26RS/6000 SP SP Switch Service Guide Priority Failing component Action 28RS/6000 SP SP Switch Service Guide Step 30RS/6000 SP SP Switch Service Guide Estart Do not perform the cable wrap test Step Do not perform cable wrap test Step Check /var/adm/SPlogs/css/out.top file Format structure LocationsNaming standard for RS/6000 SP components Location diagrams of the RS/6000 SP components Major assemblyFront and rear views of RS/6000 SP frame Figure notes2shows a front view of the RS/6000 SP multi-switch frame Front view of 49-inch frame locations. See notes below Frame locations Frame FRAExample E01-FRA-G1 Switch assembly locations Air BaffleConnector details Cable routing10RS/6000 SP SP Switch Service Guide Cable routing in a multi-switch frame F/C 2030/1 12RS/6000 SP SP Switch Service Guide Switch data cables Cable Part Plug from Plug to Number Location14RS/6000 SP SP Switch Service Guide Tools and files overview Service procedures Personal ESD requirements Ifconfig Utility see note Runs on Description FaultserviceWormRTGRc.switch File see note Location Description Rc.switch.logUsing the css.snap script Node supervisor verification Switch supervisor self-testVerification tests using Perspectives Self-test Conditions Pass sequenceSwitch supervisor verification Frame supervisor verificationDetermining the correct switch clock source Selecting appropriate switch clocksSelecting the switch clock source EclockNumber of Logical Master Clock Choice Model Frames Removing and restoring switch resourcesRemoving a switch assembly from the active configuration Restoring a switch assembly to the active configuration Viewing switch partitionsEfence of primary and primary backup nodes Replacing a switch assembly from service positionResetting the clock and bootlist after servicing a node Installing firmware updates on SP nodes Installing adapter microcode packagesAdapter Package Running diagnostics on a switch port FRU removals and replacements Handling static-sensitive devicesReplacing the switch assembly Procedures for switch assembliesRemoving the switch assembly Removing the switch front chassis cable Removing the switch fansReplacing the switch fans Replacing the switch front chassis cable Removing the switch supervisor cardReplacing the switch supervisor card Removing the switch inner chassis cableReplacing the switch inner chassis cable Removing the switch power cardsReplacing the switch power cards Removing the SP Switch power supply cards8RS/6000 SP SP Switch Service Guide Parts catalog SPS, SPS-8 Switch assembly feature view Assembly Part number Units Description Index 4RS/6000 SP SP Switch Service Guide Inner chassis assembly SPS includes all assembly in shaded Air flow Cable, front chassis SP Switch External Cables SPS SPS-8 Switch cables featureSP Switch Data Cables SPS-8 Parts catalog Multi-switch frame F/C 2030/1 Multi-switch frame F/C 2030/1 12RS/6000 SP SP Switch Service Guide Trademarks Industry Canada compliance statement United Kingdom telecommunications safety requirementsEuropean Union EU statement Radio protection for Germany For installations in JapanElectromagnetic interference EMI statement Taiwan 4RS/6000 SP SP Switch Service Guide Index Numerics ESD Switch inner chassis cable, SPS Switch partitioning 4RS/6000 SP SP Switch Service Guide Please tell us how we can improve this book Readers comments ± Wed like to hear from youHow satisfied are you that the information in this book is IBM Page IBM