Cisco Systems CGS252016S8PC manual Installation Guidelines, Verifying Switch Operation

Page 25

Chapter 2 Switch Installation

Installation Guidelines

Warning To prevent airflow restriction, allow clearance around the ventilation openings to be at least:

1.75in. (4.4 cm). Statement 1076

Installation Guidelines

Before installing the switch, verify that these guidelines are met:

Cabling must be kept away from sources of electrical noise, such as radios, power lines, and fluorescent lighting fixtures. Make sure that the cabling is away from other devices that might damage the cables.

Operating environment is within the ranges listed in Technical Specifications, page A-1

Relative humidity around the switch does not exceed 95 percent (noncondensing).

Altitude at the installation site is not higher than 10,000 feet.

For 10/100 and 10/100/1000 fixed ports, cable lengths from the switch to connected devices are not more than 328 feet (100 meters).

For cable lengths for small-form-factor pluggable (SFP)-module connections, see the SFP Module Cables, page B-4and the module documentation.

Airflow around the switch and through the vents is unrestricted. To prevent overheating, the switch must meet the minimum clearance of 1.75 inches (4.4 cm) at the top and bottom. For clearances needed for wall mounting, see specifications in Wall-Mounting, page 2-16.

Note If the switch is installed in a closed or multirack assembly, take into consideration that the temperature around the switch might be greater than normal room temperature and that special accommodations in clearance must be made.

Verifying Switch Operation

Before installing the switch in a rack or on a wall, you should power on the switch and verify that the switch passes the power-on self-test (POST).

To wire the switch to the power source, see Power Supply Installation, page 3-1

When the switch begins POST, the System LED blinks green, and the other LEDs stay green. When the switch passes POST, the System LED turns green. The other LEDs turn off and return to their operating status. If the switch fails POST, the System LED is amber.

Note Contact Cisco Systems immediately if your switch fails POST.

After a successful POST, disconnect the power from the switch. For more information, see Power Supply Installation, page 3-1See the Installing the Switch, page 2-4to install the switch into a rack or onto a wall.

Cisco CGS 2520 Hardware Installation Guide

 

78-19377-02

2-3

 

 

 

Image 25
Contents Americas Headquarters Cisco CGS 2520 Hardware Installation GuideCisco CGS 2520 Hardware Installation Guide N T E N T S Wall-Mounting Bad or Damaged Cable USB Console Port Preface Related Publications Obtaining Documentation and Submitting a Service RequestModel Description Switch ModelsCisco CGS-2520-24TC Cable-Side View Cable SidePoE Ports 10/100 Fast Ethernet PortsSFP Modules Dual-Purpose PortsType of SFP Module Model SFP Module Patch CableAlarm Ports Power-Input TerminalAlarm Input Alarm OutputUSB Mini-Type B Port LEDsSystem LED Switch Panel LEDsColor System Status Alarm LEDs Power Supply Module LEDsConsole LEDs Color DescriptionPoE LED Port LEDsDual-Purpose Port LEDs SD Flash Memory Card LEDSD Flash Memory Card Power Supply SideColor USB LED Power Supply-Side LEDsManagement Options Power Supply FeaturesNetwork Configurations Switch Installation 140F 60C Statement Verifying Switch Operation Installation Guidelines75 in .4 cm. Statement Mounting into a Rack Installing the SwitchMounting Brackets 2shows the 23-inch rack mounting brackets Attaching Brackets for 19-Inch RacksAttaching Brackets for 19-Inch Racks Attaching Brackets for 19-Inch Racks IP-30 Compliance Inserting the Rubber Plugs Inserting the Rubber Plugs Inserting the Rubber Plugs detail Attaching Brackets for 19-Inch Racks 10 Attaching Brackets for 19-Inch Racks Attaching Brackets for 23-Inch Racks11 Attaching Brackets for 23-Inch Racks Attaching Brackets for Etsi Racks12 Attaching Brackets for Etsi Racks Mounting the Switch into a Rack Attaching Brackets for Wall Mounting Wall-Mounting14 Attaching 19-inch Rack Brackets for Wall Mounting Wall-Mounting for IP-30 Compliance15 Inserting the Rubber Plugs into the Switch Holes Installing SFP Modules Installing and Removing SFP ModulesRemoving SFP Modules 17 Installing an SFP Module18 Removing a Bale Clasp Latch SFP Module Inserting and Removing the SFP Module Patch CableRemoving the SFP Module Patch Cable Replacing the SD Flash Memory Card21 Loosening the Captive Screw Device Crossover Cable Straight-Through Cable Connecting Devices to the Ethernet PortsConnecting to the 10/100 PoE Ports Connecting to the 10/100 and 10/100/1000 PortsWhere to Go Next Power Supply Modules Power Supply InstallationPWR-RGD-AC-DC Power Supply Module Power Supply Module InstallationInstalling a Power Supply Module Installation GuidelinesEquipment That You Need Grounding the Switch Dual-hole terminal lug Loosen the Screws on the Power Supply Blank Installing the Power Supply Module in the SwitchAC 5 A, DC 15 a Statement Wiring the Power SourcePSU2 11 Stripping the Input Power Source Wire AC power connection DC power connection 15 Removing the Screws Removing the Power Supply Module78-19377-02 Page Switch Post Results Diagnosing ProblemsSwitch LEDs Bad or Damaged Cable Switch ConnectionsEthernet and Fiber-Optic Cables Link Status10/100 PoE Port Connections Interface SettingsSFP Module Ping End DeviceSpanning Tree Loops Switch PerformanceSpeed, Duplex, and Auto-Negotiation Auto-Negotiation and Network Interface CardsFinding the Switch Serial Number Resetting the Switch to the Factory Default SettingsPage Physical Specifications Switch SpecificationsEnvironmental Ranges Power Requirements Power Requirements Power Specifications Power Supply Module Specifications10/100 Ethernet Ports Connector SpecificationsFigure B-2 Fiber-Optic SFP Module LC Connector SFP Module ConnectorsAlarm Ratings Alarm PortSFP Module Cables Cables and AdaptersIndustrial and Rugged SFPs Commercial SFPs100BASE-BX Cable Pinouts Extended temperature SFPsFigure B-6 Console Port Adapter Pinouts Switch Console RJ-45-to-DB-9Port DTE Terminal Adapter Device Switch Console RJ-45-to-DB-25 Port DTE Adapter Device Page RJ-45 Console Port Accessing the CLI Through the Console PortFigure C-1 Connecting the Console Cable USB Console Port Figure C-2 Connecting the USB Console CableInstalling the Cisco Microsoft Windows XP USB Driver Installing the Cisco Microsoft Windows USB Device DriversInstalling the Cisco Microsoft Windows 2000 USB Driver Installing the Cisco Microsoft Windows Vista USB Driver Uninstalling the Cisco Microsoft Windows USB DriversIP Settings Entering the Initial Configuration InformationUninstalling the Cisco Microsoft Windows Vista USB Driver Completing the Setup Program These choices appear Numerics IN-2 IN-3 IN-4