Software Setup, cont’d
Display lamp hour e-mail notification
9. Click Done. The dialog box closes.
Step 9: Create a Display Disconnection E-mail (IP model only)
To set a display disconnected
1. | Click the Monitor tab in the Global Configurator window. |
2. | Click the Add Monitor button below the Monitored |
| Conditions window. The Monitored Conditions Wizard |
| window appears. |
3. | Enter a name (enter Disconnected) in the Enter Monitored |
| Condition Name field area. The label now appears in the |
| left pane. |
4. | Click Next to specify a condition. |
5. | Select the desired equipment (for our purposes, choose the |
| Epson PowerLite 7700p) from the Subject Port window |
| and Connection Status: Disconnected from Available |
| Options. |
6. | Click Apply Condition, then click Next. |
7. | Click Next again to add an |
8. | Highlight the appropriate |
| Notification) and contacts |
| Apply Email/Contacts. |
9. | Click Done. The dialog box closes. |
Step 10: Build and Upload a Configuration
The Global Configurator project file contains all the configuration data (port assignments, product/device locations, scheduling data, etc.) you have created in Global Configurator. This is the data used to build the project's GlobalViewer Web pages for the MLC 104 IP.
Building a configuration
To build a configuration, do the following:
1. | Click the GlobalViewer tab at the left pane window to open |
| GlobalViewer Designer. |
2. | Confirm that all configured products have been given a |
| location. If not, drag each product to the desired location |
| or create new ones. |
3.Save your project file. If a project file has not been saved, GC prompts you to do so before building the configuration.
4. From the Build menu, choose Build All Configurations or Build Changed Configurations.
The Build menu
An activity bar appears, indicating that the build is progressing. The Upload Manager dialog appears when the build is complete.
MLC 104 Series MediaLink Controllers • Software Setup |