Installation, cont’d

Installing the CVEQ 100 D/SVEQ 100 D

The CVEQ 100 D and SVEQ 100 D are wall-mounted products and can be mounted into an electrical wall box. This section includes site preparation, wall box installation, and the mounting of the line driver in the wall box.

NThe line driver must be installed into an Underwriters Laboratories (UL) approved electrical wall box. The box is not included with the line driver; the installer is responsible for obtaining and installing the box.

Preparing the site and installing the wall box

Choose a location that allows cable runs without interference. Allow enough depth for both the wall box and the cables. You may need to install the cables into the wall or conduits before installing the line driver.

The line driver can be installed in a standard one-gang electrical wall box. The installation must conform to national and local electrical codes. A dimensional drawing and a cutout template of the line driver are provided in appendix B of this manual.

NThe cutout template shown in appendix B is not full size. Pay attention to the measurements shown on the template.

1. Mark the guidelines for the opening on the wall.

If the line driver will be installed in a wall box, place the box against the installation surface and draw a line on it around the outside of the box.

If the line driver will be installed without a wall box (fastening it directly to the wall), measure and mark the surface for the cutout area indicated in the cutout template.

2. Cut out the material from the marked area.

3. Check the opening size by inserting the wall box (if used) or the line driver (if no box is used) into the opening. The box and line driver should fit easily into the opening.

Enlarge or smooth the edges of the opening if needed.

4. Feed cables through the wall box punch-out holes, and secure them with cable clamps to provide strain relief.

5. Insert the wall box into the opening, and attach it to the wall or stud using nails or screws. The front edge should be flush with the outer wall surface. See the following illustration.

Wall Stud

Wall Stud

e

Installation Cable

lamp

Cable Clamp

Nails

Screws or Nails

Attaching the wall box to a wall stud

If attaching the wall box to wood, use four #8 or #10 screws or 10-penny nails. A minimum of ½" (1.3 cm) of screw threads must penetrate the wood.

If attaching the wall box to metal studs, use four #8 or #10 self-tapping sheet metal screws or machine bolts with matching nuts.

Mounting the line driver

Before mounting the line driver and if has not already been tested, test the system to make sure that the connections and settings are correct. See "Testing and troubleshooting" in this chapter.

If the system is operating correctly, the line driver can be installed in the wall. Adjust the gain and equalization, and set the Audio Out switch to Stereo or Dual Mono before fastening the line driver into the wall box. The controls and cables will be inaccessible after installation. See “Rear Panel Features and Operation" in chapter 3 for details about settings and adjustments.

Continue mounting the line driver by following the steps below.

1. Remove power from the line driver by disconnecting the power supply from the AC source.

2. Connect the output cables to the rear of the device.

3. Place the line driver through the opening in the wall and into the wall box. Take care not to damage the output cable(s), which fit behind the line driver at the back of the wall box.

2-14 CVEQ 100 and SVEQ 100 Series • Installation

CVEQ 100 and SVEQ 100 Series • Installation 2-15

Image 14
Contents Cveq 100 Series Sveq 100 Series Precautions Extron’s Warranty安全须知 中文 FCC Class a NoticeQuick Start Guide CVEQ/SVEQ 100 Series StepTable of Contents Introduction Table of Contents, cont’dOne Cveq 100 and Sveq 100 SeriesTwo InstallationFeatures IntroductionApplication Examples InstallationCveq 100 and Sveq 100 Series Installation Installation Instructions Installing the Cveq 100/SVEQFurniture mounting under-desk Furniture mounting through-desk Cveq 100 onlyPreparing the Cveq 100 for through-desk mounting Back of the rack mounting Sveq 100 onlyInstallation, cont’d Installing the Cveq 100 AAP/SVEQ 100 AAPMounting in a European cable channel Installing the Cveq 100 MAAP/SVEQ 100 MaapMounting in an external wall box Mounting the line driver Installing the Cveq 100 D/SVEQ 100 DPreparing the site and installing the wall box If the image does not appear or there is no sound Testing and troubleshootingIf the image is not displayed correctly Three OperationCveq 100 and Sveq 100 Series Operation Front Panel Features and OperationOperation Video Pinout Table Rear Panel Features and Operation Cveq 100 Rear Panel Sveq 100 AAP Rear ConnectorsOperation, cont’d Sveq 100 D Rear PanelPower supply wiring Screw connector. See the following wiring diagramsReplacing the Decora Faceplate Cveq 100 D and Sveq 100 D Gain adjustment controlEqualization EQ adjustment control Specifications, Part Numbers Accessories AAppendix aSpecifications, Part Numbers, and Accessories SpecificationsGeneral Specifications, Part Numbers, Accessories, cont’dAudio output Included parts Replacement Part number Included PartsOptional Accessories Description Part numberAccessory Part number Cveq 100 and Sveq 100 Series Specifications and Parts A-11Dimensions and Template AppendixBBCut-out Template Dimensions and TemplateDecora Models Dimensions Dimensions and Template