Sierra 215 manual L.E.D. and Relay Status Logic Fail-safe

Page 22

4.0OPERATION AND CALIBRATION OF THE Innova-SwitchFS4200 SWITCH FOR FLOW APPLICATIONS

4.1Pre-Operational Check

With the switch installed and process conditions at no-flow, the following procedure can be used to verify preliminary operation.

4.1.1Remove the instrument enclosure cover by turning counter clockwise (ccw) to expose the Innova-Switch™ Switch electronics.

4.1.2Turn on power at its source.

4.1.3Observe that either the red or green LED comes on.

4.1.4If neither lamp illuminates refer to the trouble shooting Section, 6.2.

4.2L.E.D. and Relay Status Logic (Fail-safe)

4.2.1The L.E.D.s (Red; Green) are an indication of the sensors status (ie. flow below the setpoint or flow above the set point) and are not affected by the position of the failsafe jumper J-2. The failsafe jumper J-2 changes the relay activation status allowing the user to select the failsafe power off condition most appropriate to the application. Refer to the tables below that show the logic conditions between the sensors, L.E.D. lights, relay coil and contacts for each position of the failsafe jumper J-2.

4.2.2Normal Operation (as set at factory)

The switch comes configured from the factory with the following operation with the J-2 jumper in the B(2-3) position. (Refer to Figure 8.0.)

 

 

 

 

RELAY

 

RED

GREEN

RELAY

CONTACT

SENSOR STATUS

LED

LED

COIL STATUS

STATUS

 

No Flow or Flow Below Set Point

ON

OFF

Activated

o NC

o NO

 

 

 

 

Flow or Flow Above Set Point

OFF

ON

Deactivated

o NC

o NO

 

 

 

 

IM-215 Rev-A.1

Series Innova-Switch™

Page 22 of 42

Image 22 Contents
INNOVA-SWITCH Series Before Starting This manual covers the following model numbers Special NoticeTable of Contents Introduction Description Introduction DescriptionIM-215 Rev-A.1 Series Innova-Switch IM-215 Rev-A.1 Series Innova-Switch Level Switching Thermal Differential Theory of OperationFlow Switching Gas Or Liquid Flow Innova-Switch Model FS4200 Flow Response for Three Media IM-215 Rev-A.1 Series Innova-Switch Innova-Switch Models with the CE Option Switch Block Diagram Innova-Switch Switch Assembly When Installing Your Sierra Instruments Switch Into InstallationPipe or Vessel USE a 1 1/8 Inch 28.575mm OPEN-END IM-215 Rev-A.1 Series Innova-Switch Electrical Installation Innova-SwitchSWITCH Local Electronics Field Wiring DiagramIM-215 Rev-A.1 Series Innova-Switch Innova Switch Flow Switch Remote Electronics Option Field WiringConnections Remote Electronics Cable TerminationInnova-SwitchSWITCH Remote Electronics Field Wiring Diagram L.E.D. and Relay Status Logic Fail-safe Innova-Switch Electronics For Optimum OPERATION, Calibration Must be Accomplished Pre-Operational Check RED Green Relay Contact Sensor Status LED Innova-Switch Electronics Calibration Level IM-215 Rev-A.1 Series Innova-Switch IM-215 Rev-A.1 Series Innova-Switch Cleaning Intenance and Trouble ShootingTroubleshooting Special Notice Input Power Specifications TypeOperating Temperature Process ConnectionsWarranty Warranty and ServiceService Connector Plates Volume Flow Conversion Chart To Convert from Multiply byFlow Conversion Chart Flow of Water Through Schedule 40 Steel Pipe Options Livetap LT Variable Insertion Thermocouple Output to and 10.4 RTD Output RT IM-215 Rev-A.1 Series Innova-Switch