System Description
Synchronizing activity takes place automatically once the preferred source is chosen and a manually initiated “SYNCHRONIZE SYSTEMS” signal is given. Visual indicators show that the systems are synchronizing and when the systems are ready for the manually initiated, automatically controlled paralleling sequence.
Continuous Tie/Transfer/Parallel Control
The transfer load and tie controls operate the tie breakers between systems in a sequential manner to allow paralleling and
With the two systems operating in parallel, only one bypass circuit is active. Should something occur that requires the UPS to automatically transfer to bypass, then all the load will be supplied through the static switch and bypass circuit breaker of the system that was selected as the preferred source.
When the two systems are paralleled, it is possible to isolate and then shut down one system entirely for maintenance. The system to be shut down must be the one that is not the designated preferred source. Shutdown is accomplished by first opening the System Isolation Breaker of the selected sys- tem. Once this action is taken, all the load remains on the preferred system.
The three load sharing control circuits between systems are disconnected with the opening of the Sys- tem Isolation Breaker. At this time, sync control of the
Restart of the systems under maintenance is accomplished in the normal manner. Once the system has been brought
Taking the systems out of parallel operation is manually initiated. The tie breaker automatically opens separating the loads onto their respective UPS systems. The intersystem power sharing is dis- abled and the sync circuits revert to independent operation.
1.5.4Tie System Components
See Figure 4.
A Liebert
1.Two complete, independent UPSs with individual load buses, each with the capability to source the combined critical load of the two load buses. Each of the two UPSs may be a
2.Two discrete system input sources, each with the capacity to source the combined critical load. The two input sources need only be acceptable with regard to frequency and voltage. The two sources do not require an
3.Two discrete bypass sources, each with the capacity to source the combined critical load. The two bypass sources need only be acceptable with regard to voltage and frequency, such as the utility or an emergency generator, and are not required to be
4.One system isolation and tie switchboard containing system isolation breakers and tie breaker(s).
5.Tie Control Unit, wall or floor mounted or installed in the tie switchboard.
6.Optional maintenance bypass breakers and test load distribution.
8