5.4 User Interface Display/Control Module Functions

Each OVATION™ ATS User Interface Display has five (5) buttons that program and control the automatic transfer switch and control certain generator functions. NOTE: The generator may also have controls that program certain generator features that are NOT programmable from the OVATION™ ATS. See generator Installation and Owners Manual for further generator information.

Table 5.4

BUTTON

 

FUNCTION

DESCRIPTION OF FUNCTION

TRANSFER

 

1. Sets load transfer

TO BE USED BY QUALIFIED SERVICE PERSONNEL ONLY.

 

 

1. Sets to transfer/not transfer load to generator during exercise.

 

 

during generator

Factory setting is NO transfer during generator exercise. To

 

 

exercise cycle

transfer load during exercise, press TRANSFER, then within 5

 

 

 

seconds, press SERVICE; LED 5 flashes once if set successfully.

 

 

 

To change back to NO transfer load during exercise, press

 

 

 

TRANSFER, then within 5 seconds, press SERVICE; LED 5 flashes

 

 

 

twice if set successfully.

 

 

 

When TRANSFER is pressed after EXERCISE is pressed, load will

 

 

2. Sets generator start

transfer 1 time to generator then back to utility 5 minutes before

 

 

end of exercise cycle.

 

 

delay.

2. Sets generator start delay after utility power loss. Factory

 

 

 

setting is 5 second delay. Press TRANSFER then within 5 seconds

 

 

 

press EXERCISE; all LEDs flash once then LED 1 lights indicating

 

 

 

5 second start delay. Continue to press EXERCISE until desired

 

 

 

LED lights. LED2=15min, LED3=30min, LED4=45min,

 

 

 

LED5=60min delay. When the desired LED is lit, press TRANSFER

 

 

 

to select delay and terminate function.

GENERATOR

 

Starts and stops

To start generator, press once. To stop generator, press twice.

START/STOP

 

generator

Will override all generator and transfer switch time delays.

EXERCISE

 

Starts generator

During the exercise cycle, generator cranks and starts, the red

 

 

exercise cycle

GENERATOR POWER light comes on (if generator power is

 

 

 

acceptable) and load will transfer to generator power if set to

 

 

 

transfer (see TRANSFER above) then GENERATOR LOAD light

 

 

 

comes on. Generator runs for 10 minutes (5 minutes under load

 

 

 

if load is transferred) and stops. GENERATOR POWER and

 

 

 

GENERATOR LOAD lights shut off. To cancel EXERCISE, press

 

 

 

RESET once.

RESET

 

Reboots controller

Reboots controller (controller will retain programmed settings).

 

 

 

Resets generator exercise clock. Performs one transfer cycle of

 

 

 

UTILITY MAIN circuit breaker and terminates with UTILITY MAIN

 

 

 

circuit breaker ON and GENERATOR MAIN circuit breaker in OFF

 

 

 

position. Clears most faulty codes. Will not clear fault codes if

 

 

 

fault cause is not corrected. During EXERCISE or SERVICE

 

 

 

programs, overrides all time delays and terminates test.

SERVICE

 

1. Tests actuator

TO BE USED BY QUALIFIED SERVICE PERSONNEL ONLY.

 

 

1. Hold +press EXERCISE: Cycles Actuator Module continuously

(Use sharp

 

2. Calibration utility

– used to test mechanism. Press RESET to terminate test.

pencil or ball

 

2. Required when certain electrical parts are replaced. Contact

point pen to

 

3. Simulates utility

Gen/Tran for Calibration Procedure. See Section 8.4.

press Service

 

3. Press once: disconnects UTIL sense circuit to simulate utility

Switch)

 

power loss

power loss

 

 

 

Press twice: reconnects UTIL sense circuit to simulate utility

 

 

 

power restored.

 

 

 

NOTE: after 1 press, UTIL sense circuit will auto reconnect after

 

 

 

5 minutes; SERVICE routine is terminated without further

 

 

 

operator intervention.

24

Image 24
Contents Ovation Series Safety Precaution Definitions Table of Contents Introduction General DescriptionStandard Configurations How the Ovation Series Automatic Transfer Switch Works Retrofit NEW Construction or RetrofitModel ATS1001D/R Key ComponentsModel ATS2002R PowerPause Load Management Modules Optional User Interface Display UIDUtility and Generator Source Circuit Breakers Remote PowerPause Relay Box Optional Surge Protection Module OptionalStandards Compliance Compatible Equipment Compatible GeneratorsCompatible Circuit Breakers Compatible Circuit Breaker TypesPreparing for Installation Other Items YOU MAY NeedPowerpause Load Management Priority Page Installation and Wiring Internal Wiring Diagrams Models ATS2001D/R Internal Wiring Diagrams Model ATS2002R Then Pull UP Here As a Generator subpanel Models ATS1001D/R Load CenterFunction ON/OFF RUNConnecting the Low Voltage Cable to the Generator Page Programming the System Dial Name ModelNumber Reset ServiceTransfer GeneratorStartup and Testing Energizing the Transfer SwitchTesting the Transfer Switch Preliminary ChecksRe-Installing Covers and Labeling Circuits Generator Battery MonitoringTroubleshooting Problem Possible Cause Solution SectionBattery fails to Button commandsDelay between Exercise, orMaintenance and Service MaintenanceExploded Views and Replacement Parts List Product RegistrationModel ATS1001D QTY PART# Description TypeModel ATS1001R QTY PART# Description TypeModel ATS2001D QTY Part Description SourceModel ATS2001R QTY Description SourceModel ATS2002R SourceDescription 07/16/10 PN 530001 Rev D