Configuration

Connection of Load to the PDU

Connecting load to the PDUs

Connect the load evenly between the 3 phases to avoid overloading one particular single phase. The total output capacity of the PDU is approximately twice the output capability of the UPS, meaning that the UPS would be over-loaded if all outlets were loaded to their

Note rating. Load status on the individual phases can be found through the UPS display or through the web interface.

Equipment connected to the 3-phased output may require overcurrent protection with a lower rating than the 3-phased output.

Note

For 3-phased outputs, the highest current may be in the Neutral conductor at non-linear loads (up to 173%).

Note

Connecting 1-phase load to PDU I

 

 

 

 

 

 

 

 

 

 

 

 

Set the applicable breaker to the OFF position.

Guide the load cable down through the top hole.

Insert the plug from the load into the C19 outlet.

Secure the plug by inserting the locking brackets.

Set the applicable breaker to the ON position.

990-2820A

Smart-UPS® ISX 30-40 kVA, 400V Operation

17

Image 23
Contents Operation Page Companion manuals How to find updates to this manualAbout this Manual Page Contents Configuration Safety System Overview OverviewOpening front and rear doors System ComponentsUser interface front User interface area rear Battery ModuleRear cover of this manual DisplayOverview The Display Menu treeControl functions Basic display navigation principlesStatus views Select YES, Turn Load onLogging Clock set-upSelect View Statistics Display setup Alarm thresholdDiagnostics screen Vol VolumeOperation Modes OperationOperation Procedures Turn into normal operation from mechanical bypass operation Connection of Load to the PDU ConfigurationConnecting load to the PDUs Connecting 1-phase load to PDUConnecting 3-phase load to PDU PDU output breaker ratings Disconnecting load from the PDUsHow to return parts to APC Parts ReplacementHow to determine if you need a replacement part How to remove Battery Modules How to install a Battery Module How to replace a Network Management Card Display messages TroubleshootingTroubleshooting Parts Replacement Troubleshooting Parts Replacement Restart Power applicationVoltage confirmation Page 05/2006 APC Worldwide Customer Support990-2820A