American Power Conversion VT ISX manual How to install a Battery Module

Page 28

Configuration – Parts Replacement

To release the battery from the lock mechanism, one person gently pushes the battery upwards again and pulls it out, while the other person supports the battery.

How to install a Battery Module

If additional batteries are needed for extra run-time, or if you install battery replacement modules etc., follow the below procedure:

Wait until you are ready to power up the system before installing Battery Modules in the UPS. Failure to do so can result in a deep discharge of the batteries and cause permanent damage (the time from the battery installation time till the UPS is powered up should

Caution

not exceed 72 hours or 3 days).

 

BATTERY UNIT

BATTERY UNIT

Install the Battery Modules in the lowest available bay.

Position the Battery Unit to slide in between the grooves and push completely into the UPS to ensure connection.

If a problem is reported, ensure that the modules in question are correctly installed. If the problem persists, refer to the Troubleshooting section of this guide.

Allow for a 24-hour recharging period of the batteries after system start-up / battery replacement for battery monitoring data to become fully reliable.

Note

22

Smart-UPS® ISX 30-40 kVA, 400V Operation

990-2820A

Image 28
Contents Operation Page About this Manual How to find updates to this manualCompanion manuals Page Contents Configuration Safety Overview System OverviewSystem Components Opening front and rear doorsUser interface front Battery Module User interface area rearDisplay Rear cover of this manualMenu tree Overview The DisplayBasic display navigation principles Control functionsSelect YES, Turn Load on Status viewsClock set-up LoggingSelect View Statistics Alarm threshold Display setupVol Volume Diagnostics screenOperation Operation ModesOperation Procedures Turn into normal operation from mechanical bypass operation Configuration Connecting load to the PDUsConnecting 1-phase load to PDU Connection of Load to the PDUConnecting 3-phase load to PDU Disconnecting load from the PDUs PDU output breaker ratingsHow to determine if you need a replacement part Parts ReplacementHow to return parts to APC How to remove Battery Modules How to install a Battery Module How to replace a Network Management Card Troubleshooting Display messagesTroubleshooting Parts Replacement Troubleshooting Parts Replacement Power application RestartVoltage confirmation Page 990-2820A APC Worldwide Customer Support05/2006