American Power Conversion MX28B2400+27V, MX28B1200 AC Service and Ground Connections, Ventilation

Page 20

MX28B-1200+27V PRODUCT MANUAL

Rev 1

5.1.7Ventilation

The rectifiers have fans that provide front to rear airflow for internal cooling. The MX28B1200 housing should mounted to allow free airflow from the front and out the top of the unit. [Refer to Section 4.10 for environmental characteristics.]

5.2AC Service and Ground Connections

*****WARNING *****

Ensure that all of the DC and external AC circuit breakers are in the OFF position prior to connecting service to the power plant. Confirm that all voltages have be en removed including any battery sources before proceeding.

The MX28B DC power plant requires the supply of 208/220/240V AC, single -phase, 50/60 Hz power through individual external 80-amp circuit breakers to the AC input terminal block connections for each rectifier shelf the system. Each rectifier shelf has four 20-amp breakers, each serving one rectifier. The AC Grounding wiring, from the Earth terminal block to the individual shelves is factory installed for each shelf installed. Connections to the AC input connector for each rectifier, is factory installed.

AC Grounding wires

Figure 5-2 AC Wiring conduit

Figure 5-3 AC Wiring Terminal

14

Image 20
Contents Model MX28B1200/2400+27V Battery Temperature Probe Description Part NumberDC Distribution Options +24V LVD Options +24VRevision Date Description 09/12/2001 Initial releaseTable of Contents SETUP, ADJUSTMENTS, and Operation Page Precautions IntroductionInspection upon Receipt of Goods GeneralConcealed Damage Return of Damaged GoodsGeneral Provisions Warranty ReturnsWarranty Repair or Replacement Exclusions and Limitations Description MX28B-1200/2400+27VMX28B1200/2400+27V System Diagram Converters Power Output CapacityRectifiers AC Input Power Control UnitBattery connections +24V DC Distribution48 V DC Distribution from Converters Optional DC Distribution Compliance Environmental Mechanical Safety Precautions PreparationRecommended Tools Recommended Test EquipmentRoom/Locations MountingAC Service and Ground Connections VentilationBattery Disconnect Connecting the Cables Cable Sizing ConsiderationsRectifier Installation Converter InstallationAlarm Connections Alarm Interface PC BoardExternal Alarm Inputs Alarm OutputsConnecting The Loads DC Circuit BreakersInstallation of Circuit Breakers 2.2 -48V Circuit Breaker Load ConnectionsBattery Temperature Probe Installation Power-Up and CheckoutApply AC Power System Parameters Verification/AdjustmentFull System Power Up SETUP, ADJUSTMENTS, and Operation User InterfaceSnmp Interface External Alarm InputsAlarm Output Relays Parameter Locations, Descriptions, and Default Values System SET-ALM AlarmsStatus Setup PIN DateOUT-RLY RLY-MAP AliasDiag Modules Rect SET-ALMParam InfoCirbkr SET-ALM Fuse SET-ALMComp Alias Fuse LVD SET-ALMBatt SET-ALM PIN OEM MX28B-1200+27V Product Manual RevParameter Description Display Screens Default Settings Conv LV Alm OFF 40.0 CBatt Disc Alm m+ Conv Fail Safem+ Cir Bkr 1 Alm m+ Out-Rly LVD1 LVD2