Rev 1 |
5 INSTALLATION PROCEDURES
5.1 Preparation
5.1.1Recommended Tools
∙Standard selection of insulated hand tools.
∙Proper tools for crimping the selected cable lugs.
5.1.2Recommended Test Equipment
∙Digital Multimeter
5.1.3Equipment Inspection
Remove equipment from packing material and inspect for shipping damage to verify the safety and operational suitability for the installation site. [Refer to Section 1.3]
5.1.4Safety Precautions
***** WARNING *****
The power plant is supplied from a nominal 230V AC, 50/60 Hz source. Keep All AC input enclosure covers in place when the system is operational or energized.
***** CAUTION *****
Handling or touching the controller boards located inside this unit without being electro statically discharged (grounded to the frame) may cause extensive damage to the electronics. Before touching or handling the controller boards, it is recommended that an ESD wrist strap be utilized.
***** WARNING *****
Hazardous energy levels are present on bare conductors in the +24 and
It is recommended that:
∙Any jewelry, rings or watches be removed while working on this equipment.
∙Handles of all wrenches, screwdrivers, cutters and pliers be insulated.
∙Shafts of screwdrivers be wrapped in electrical tape or otherwise insulated.
12