American Power Conversion CTFLP Series Operation, Initial Startup and Performance Verification

Page 10

Chapter 3 Operation

Initial Startup and Performance Verification

1.Switch the utility circuit breaker ON.

2.Verify that the FLM is switched ON.

3.Measure the voltage at the Coax connector ensuring that 60VAC or 90VAC are present depending on the power supply installed. The green Indicator lamp on the bottom of the unit should be illuminated.

4.Replace the doors on the enclosure.

Shut Down

1.Switch the FLM OFF.

2.Switch the utility circuit breaker OFF.

Auxiliary Power Supply

1.Set up an auxiliary utility generator and calibrate to 60 Hz ± 1 Hz.

2.Switch the utility circuit breaker OFF.

3.Unplug the utility input cord from the FLM and attach it to the generator extension cord.

For details regarding available options see the APC web site www.apc.com.

8

Image 10
Contents BroadBand Ctflp Series Page Electrical Warnings Overhead Warnings SafetyGeneral Information LiftingSpecifications Environmental SpecificationsCtflp Enclosure Installation and MaintenanceUnpacking Models SupportedWiring Ctflp Enclosure InstallationBottom View Page Installing the FLM Power Supply Ensure the Ctflp module circuit breaker is OFFIndex Description Initial Startup and Performance Verification Auxiliary Power SupplyOperation Shut DownMaintenance Troubleshooting and MaintenanceOperation Interval Wiring Harness Replacement CleaningVisual Inspection Indicator Lamp Replacement Euro Block ReplacementService Service, Contact and Warranty InformationHow to Contact APC Limited Warranty Regulatory Approval