Installing the FLM Power Supply

Ensure the CTFLP module circuit breaker is OFF.

1.Unlock and open the front enclosure door. To remove the front door from the enclosure, squeeze the edges of the enclosure together. This will allow the pins at the top of the door to slip out of the side enclosure panels.

2.The top door of the enclosure is hinged on the back edge.

3.Lower the FLM module into the enclosure so that the guide pins on the FLM and the enclosure engage.

4.Push the module until a light “snap” is felt as the contacts lock into place.

5.Pull lightly on the module. If properly seated the module will not easily disengage.

6.Turn the utility power ON.

7.Turn the module breaker switch ON.

8.The green Indicator lamp should be ON.

9.Using a voltmeter, verify utility voltage at the coax connection.

6

Image 8
Contents BroadBand Ctflp Series Page Safety General InformationElectrical Warnings Overhead Warnings LiftingSpecifications Environmental SpecificationsInstallation and Maintenance UnpackingCtflp Enclosure Models SupportedBottom View Ctflp Enclosure InstallationWiring Page Installing the FLM Power Supply Ensure the Ctflp module circuit breaker is OFFIndex Description Auxiliary Power Supply OperationInitial Startup and Performance Verification Shut DownOperation Interval Troubleshooting and MaintenanceMaintenance Visual Inspection CleaningWiring Harness Replacement Indicator Lamp Replacement Euro Block ReplacementHow to Contact APC Service, Contact and Warranty InformationService Limited Warranty Regulatory Approval