American Power Conversion 240-320kW 400V manual Intersystem Synchronization Unit

Page 56

Options/Accessories

6.3Intersystem Synchronization Unit

Intersystem Synchronization Unit System (ISU System)

The ISU system consists of inter-connected ISUs. One ISU system may consist of up to 5 ISUs, regardles of ISU configuration. The ISU system synchronizes the voltage of parallel operation systems running in battery operation.

The ISU system may also include one or more external synchronization sources, e.g. a gen-set or a non-APC Silcon UPS system.

Synchronization accuracy of the ISU is better than 2o.

Schematic overview of ISU system (example):

UPS 1A

UPS 3A

UPS 1B

Parallel

Operation

System 1

ISU

1

ISU

3

Parallel

Operation

System 3

UPS 1C

UPS 2A

 

ISU System

UPS 3C

UPS 2B

Parallel

Operation

System 2

ISU

2

ISU

4

ISU

5

UPS 2C

UPS 4

Ext. sync Source

UPS 3B

Intersystem Synchronization Unit (ISU)

The ISU is an active part of an ISU system, serving as the interface to the sources and the ISU system.

The ISU can be connected to a parallel UPS configuration, using the standard parallel communication controller in the parallel operation system.

(See Intersystem Synchronization Unit User’s Manual for further details.)

990-4045a

56

Installation Guide APC Silcon 240-320kW 400V UPS

Image 56
Contents APC Silcon 240-320kW 400V UPS Installation Guide Thank You Installation Guide APC Silcon 240-320kW 400V UPSSafety Symbols used in this manual Contents System Specifications Warranty10.0 How to Contact APC AppendixIntroduction IntroductionTools and Equipment ToolsUnpacking UnpackingInstallation InstallationRequirements on Site Height mm Width mm Depth mm2 825mm Cabinet for Isolation Transformer or Switch Gear Footprint1 1600mm Cabinet for 240-320kW UPS 3 1600mm Cabinet for Isolation TransformerConnecting the UPS External ConnectionExternal Connection Right side viewOutput Fuses240kW 320kWSystem Integration Interface Connections Parallel Board Terminal Blocks X003/X004 Anxiliary ContactsX005 Output Relays Parallel BoardExternal Connection Power Cables External Control CablesRelay Board RelaysRelay Message Alarm-trigging Events Number Relay Board/Relay FunctionsSee .2 System configuration Communication Interface Board Connecting of APC Silcon Tripel Chassis Safety Warnings APC Silcon Triple ChassisProduct Description Monitoring PortOptional Power Input Installing Management PeripheralsLEDs If the LED is… Then the Silcon Triple Chassis…Installing Management Peripheral Cards Order of Management Peripheral CardsManagement Priority Position Peripheral Card Daisy-chaining the APC Silcon Triple ChassisManagement Peripheral Draw mA If Problems Persist TroubleshootingProblem Possible Cause Solution Product Specifications Monitoring Port Pin Assignments External Connection Environmental Power, Physical, and Environmental SpecificationsPhysical APC Silcon Battery Cabinets Important Safety InstructionsSilcon Installation of BatteriesDiagram UPS with Battery Cabinet Battery Breaker Box/Fuse-box Battery Breaker Box Ampere Connection Max Dimensions Weight Rating Cable ShortCircuit Current kA 240 kW 320 kWAPC Battery Breaker Box Connection Diagram External Connection Parameter Setting Comments Programming ParametersProgramming Parameters ParametersProgramming Keys System Configuration Programming Example Switch to Bypass OperationSystem Configuration Parameters password protected Programming Example Change Charge Voltage to Change parameters by pressing Description of Settings Programming Parameters for Advanced Parallel OperationBattery Monitor Programming exampleService Bypass Panel for Single Operation Options/AccessoriesOptions/Accessories Options/Accessories Operating The External Service Bypass Switch Display showsSwitching from External Bypass to Normal UPS Operation Lamp indication On Servive Bypass PanelService Bypass Panel for Parallel Redundant Operation Two Parallel Systems with Service Bypass Panel Options/Accessories H002a Action Options/Accessories Display shows Lamp indication On Service Bypass PanelAction Isolating One UPS for Service/Maintenance Following can be carried out on any UPSSwitching Back to Normal Parallel/Redundant Operation Intersystem Synchronization Unit ISU Intersystem Synchronization UnitIntersystem Synchronization Unit System ISU System Standard Short-haul RS232 Modem Async Remote DisplayExtension of Remote Display Communication Distance Connections Without Converter Host DTE Remote Display DTEConnections With Converter Pin Connections for cable from host to ME800A-R2 HostRemote Display Power Supply Remote Display CablesCommunication Fault Remote Display SettingAlarms Remote Display UseHeight mm Width mm Depth mm Weight kg Isolation TransformerConnecting Isolation Transformer External External PE Input Fuses Input CableFM a 120 DIN gL typesOptions/Accessories Cable mm2 Signal Isolation External External PEInput Input Cable Output Temp Fuses* FM 150 185Options/Accessories Options/Accessories Options/Accessories Options/Accessories Options/Accessories System Specifications System SpecificationsTechnical Data Dimensions / WeightAPC Silcon Series Limited Factory Warranty WarrantyWarranty Appendix Installation Planning DataAppendix Appendix How to Contact APC How to Contact APCAPC Corporate Fairgrounds Road West Kingston, RI APC Denmark Silcon Allé DK-6000 Kolding