3-5.A/CHEADASS'YREMOVAL(See Fig.3-10)
a. Remove one nut hex
from the A/C HEAD POST
of the MAINBASE.
b. Remove the A/C HEAD ASSEMBLY
from the MAINBASE.
c. Remove the A/C HEAD SPRING
from the
A/C HEAD ASSEMBLY .
NOTE:
After reassembling, adjust the TAPE TRANSPORTING SYSTEM refering to chapter 5 "ADJUSTMENT OF THE TAPE TRANSPORTING SYSTEM".
After adjusting the TAPE TRANSPORTING SYSTEM, spread the A/C HEAD/NUT, AZIMUTH SCREW, and TILT SCREW with LOCKING PAINT.
3-6.L/CBRACKETASS'YREMOVAL(See Fig.3-11)
a. Remove one screw
from the L/C BRACKET ASSEMBLY
.
b. Remove the L/C BRACKET ASSEMBLY
from the MAINBASE.
3-7.PINCHLEVER
TOTALASS'YREMOVAL(See Fig.3-11)
a. Remove one POLY WASHER
from the PINCH LEVER POST of the MAINBASE.
b. Unhook the PINCH LEVER SPRING
from the hook of MAINBASE
and remove the
PINCH LEVER TOTAL ASSEMBLY
.
CAUTION:
Take care not to coat GREASE, OIL or other substances on the surface of the PINCH ROLLER .