Theta Digital LC3015-2 manual Electrical Requirements, Preparation

Page 8

LC3015 Theta Pre-Install Check List

(checklist page ii)

Electrical Requirements

Electrical power has been connected to the top of the disconnects for each of the following:

￿NC cabinet

￿Laser power supply

￿Dust collector

￿Chiller

Preparation

￿Chiller tank has been filled with distilled water only.

(on the CKD chiller, water hoses must be connected before filling tank)

￿All plastic and paper coverings removed.

￿Clean protective coating (cosmoline) from ball screws and LM guides.

￿Each system component has been placed per the layout

￿Shop air plumbed and connected to the machine. See page 7 for details.

￿Shop air plumbed to dust collector with regulator. See page 7 for details.

I certify that each of the actions checked off above have been performed.

I understand that all of the above are needed for a successful installation and if any of the require- ments are not met the installation will be delayed and I will be billed for one day’s service at normal service charges, including expenses.

If the delay is to be more than one day the Engineer will be rescheduled to begin the installation on the first available Monday after the problem has been corrected and I will be billed for the additional travel expenses also.

Signature

Title

Date

ii

Image 8
Contents Theta LC30152 Revision history Document titleApplies to Contents Dust Collectors Table of Figures Electrical connect 230 VAC Items to be Obtained Pre-Installation ChecklistPlacement of the Machine and Components Electrical Requirements PreparationDescription of the Major Components Major Components Size and Weight of Major Components Basic Specifications Feature SpecificationLaser and Production Cutting Specifications Supply Requirements Other Requirements Air specifications ISO 8573.1 standard ConnectionsLaser Pre-mix Gas BOC GasesLaser Pre-mix Gas Specification Gas Pre-mix ratiosPurity MoistureGas Assignment Inlet Port Assist Gas RecommendationsOxygen Purity Machine Dimensions LC3015 Theta Front View Machine from shuttle endMachine Dimensions LC3015 Theta Side View Machine from operator sideMachine Dimensions LC3015 Theta Plan View Machine from topPlanning The Location of the Machine Chiller Chiller Dimensions Orion ChillerDust Collectors Torit DFT3-18Torit DFT3-18, side view Farr GS-12 Machine Foundations Machine Foundations Cross Section Foundation plan and side viewsFoundation End View Foundation right end viewBolt Detail Lifting Installing The Air Supply Grounding resistance Installing The Electrical Power SupplyLaser and CNC grounding Electrical connect 460 VAC Electrical connect 230 VAC LC3015 Theta User Installation Guide October CNC power connect, Figure Power cable Breaker Protective Coatings Revision history Contact InformationVersion Details Company/group Purpose Phone