Cisco Systems 78-10588-03 manual Installing the Chassis Running Online Tests

Page 27

Chapter 3 Installing the Chassis

Running Online Tests

Step 3 Use the ocmstate command to switch on the local loop. Now you can measure the output power at point F. Afterwards, switch off the local loop. To measure at points B or C, follow Steps 1 and 2 and then Step 4:

Step 4 Use the ocmstate command to switch the remote laser to “forced ON” to overcome ALS. Then measure at points B and C. If you want to measure the input at points D or E, follow Steps 1, 2, and 3 and then Step 5.

Step 5 Use ocmstate to activate the remote loopback on the remote side of the link.

The link comes up. All lasers and receivers at the channel module are on and the remote receiver and the remote transmitter at the channel module on the remote side of the link are on. The local transmitter at the channel module at the remote side of the link is also on to allow measurements.

In case you do not have an adequate external modulated light source, you can use the modulated light (100 MHz) of the pilot laser of the Cisco Metro 1500 series system’s RSM (only an option if your Cisco Metro 1500 series system is equipped with an RSM). In this case, in Step 2 you connect the local RSMs B/R (output of the pilot laser) to the connector labeled L/R (local receiver) of the channel module. The output of the pilot laser is sent against traffic.

Note Do not forget to set or enable clocks, disable loopback and enable automatic mode for the RSM before putting the Cisco Metro 1500 series units into service.

 

 

Cisco Metro 1500 Series Hardware Installation Guide

 

 

 

 

 

 

78-10588-03

 

 

3-27

 

 

 

Image 27 Contents
Before Installing Installing the ChassisUnpacking and Inspecting the System Mounting the System Maintaining a Network RecordInstalling the System Nemi master Installing the Nemi ModuleInstalling the Chassis Installing the System Demi location Installing the Demi ModuleConnecting Power Fan module Connecting AC PowerFront Panel of the Cisco Metro Installing Terminal Blocks US Version Connecting DC PowerTerminal blocks Holders Power supplyConnecting Wires Fan module Fuse holders DC Power connectorsSelv Application Power Cable Blue Brown Green/yellow Ferrules 48 VDC Application Power CablePower Type Fuse Type No. of Fuses Power Consumption and Power Supply FusesGrounding the Chassis Cleaning the SystemCleaning the Connectors Cleaning the ChassisInstalling the Chassis Cleaning the System Power On/Off Removing the Power Supply ModuleWCM RSM Nemi DMX Power 1 PowerDetermining Power Supply Status Fan module Fuse 11 Rear View of Power Supply ModuleVerifying Connections Running Online TestsMeasuring Channel Outputs and Channel Budgets Installing the Chassis Running Online Tests Problem Probable Cause Solution TroubleshootingProblem Probable Cause Solution Installing the Chassis Troubleshooting