Honeywell 4909 CPVC manual Replacement Parts, Voltage and Time Limits for Platinizing Cells

Page 26

4909 CPVC Conductivity Cell Insertion/Removal Assembly Operations Manual

4.3 Replacement Parts

Table 4-1 Replacement Parts

Description

Part Number

Complete Assembly

Cell Assembly

Complete CPVC Removal Device

Universal Head Parts

Platinizing Solution (3 oz. bottle)

Cell Guard Tube (0.01, 0.1, and 1.0 Constants Only)

Support Tube, 1/2” NPT Sch. 80, CPVC (12” Immersion)

Support Tube, 1/2” NPT Sch. 80, CPVC (6” Immersion)

Junction Box

Cell Extension Leadwire (Table III other than 333)

Three conductor 18 gage cable PVC (105°C max.) Three conductor 18 gage cable Tefzel (150°C max.)

See Figs. 1-5 and 1-6

Cat. 4908

31074357

See Fig. 1-6

31103011

065602

074344

074343

31316260

834059

834086

9782/7082 Standard Ranges Up to 500 ft.

Three conductor, 18 gage cable (Belden 9493)

834059

and Coax Cable (Belden 9259)

835024

Up to 1000 ft

 

 

Four conductor (3 used), 16 gage cable,

834055

Belden 9494 or equivalent and Coax Cable (Belden 9259)

835024

9782/7082 Wide Ranges

 

Up to 500 ft - Four Conductor, 18 gage

31834052

Up to 1000 ft - Four Conductor, 16 gage

834055

Table 4-2 Voltage and Time Limits for Platinizing Cells

DC Voltage

1.5

3.0

6.0

12.0

5

----

200sec 80 sec

----

Cell Constant

10

20

 

 

----

----

 

 

240 sec

----

 

 

100 sec

180 sec

 

 

----120 sec

25

----

----

200sec

150sec

50

----

----

300sec

240sec

18

4909 CPVC Conductivity Cell Insertion/Removal Assembly– Operations Manual

7/99

Image 26
Contents 70-82-25-19 Rev 7/99 Copyright, Notices, and Trademarks Revision 1- 7/99References AbstractRevision Notes ContactsOrganization Telephone Address Honeywell TAC Voice Contents Platinization and Platinum Black Figures Page 4908 Conductivity Cell IntroductionOverview Temperature/Pressure* Range 31074357 Removal DeviceValve NPT Plug Conductivity Cell Conductivity Cell Adapter Set Screw #6-32 Binding Head Page Specifications and Model Selection Guide SpecificationsWeight Integral Automatic Temperature CompensationLeadwire Model Selection GuideSelection Table VII Options Location and Position InstallationRequirements ConsiderationsMounting into the Process Prepare AssemblyInitial Prep Insertion Removal Electrical ConnectionsRED White Green Replacing Removal Device Parts Maintenance and Replacement PartsTo Clean The Cell Voltage and Time Limits for Platinizing Cells Replacement PartsReplacement Parts Platinization and Platinum Black RED Green Direct Cell to Analyzer Installation #2 TempNote 5 Compensator Page Page Industrial Automation and Control