Honeywell 4909 CPVC manual Removal, Electrical Connections

Page 22

4909 CPVC Conductivity Cell Insertion/Removal Assembly Operations Manual

3.5Removal

1.REDUCE PROCESS PRESSURE TO 50 PSIG OR LESS. Shut off purge line, if used. Disconnect wiring connections if X1 is selected for Table IV in the MSG.

2.DO NOT STAND BEHIND THE TUBE WHEN PERFORMING THIS STEP. While holding the compression handle from turning, turn the support grip two turns counterclockwise. Loosen the compression handle until the process pressure pushes the cell and support tube assembly out to its internal stop. If necessary, pull out by hand until stop is reached.

3.Close the ball valve. If the valve does not close easily, make sure the support tube is pulled all the way back.

4.Completely loosen the compression handle to withdraw the cell.

3.6Electrical Connections

The terminal board connections for recorder or analyzer are given in the appropriate directions furnished with the measuring instrument.

When the cell assembly includes a built-in temperature compensator, all leads are used. The cell is connected between black and white and the compensator is between red and white, except when MSG Table III=333. In this case, the built-in temperature compensator is between red and green. See Figs. 5-1 and 5-2 when wiring cells with MSG option=333.

To avoid the possibility of ac pick-up in the cell leads, separate them from all AC line voltage wiring or run them in a separate grounded conduit.

Cells are available with leadwire up to 20 feet as specified in the MSG assembly. For distances greater than 20 feet, use the required length of cable and a junction box, both listed in Section 4.3. For assemblies supplied with a Universal Head, Fig. 3-2, a junction box is not required.

14

4909 CPVC Conductivity Cell Insertion/Removal Assembly– Operations Manual

7/99

Image 22
Contents 70-82-25-19 Rev 7/99 Copyright, Notices, and Trademarks Revision 1- 7/99References AbstractRevision Notes ContactsOrganization Telephone Address Honeywell TAC Voice Contents Platinization and Platinum Black Figures Page Overview Introduction4908 Conductivity Cell Temperature/Pressure* Range 31074357 Removal DeviceValve NPT Plug Conductivity Cell Conductivity Cell Adapter Set Screw #6-32 Binding Head Page Specifications and Model Selection Guide SpecificationsWeight Integral Automatic Temperature CompensationLeadwire Model Selection GuideSelection Table VII Options Location and Position InstallationRequirements ConsiderationsInitial Prep Prepare AssemblyMounting into the Process Insertion Removal Electrical ConnectionsRED White Green To Clean The Cell Maintenance and Replacement PartsReplacing Removal Device Parts Replacement Parts Replacement PartsVoltage and Time Limits for Platinizing Cells Platinization and Platinum Black RED Green Direct Cell to Analyzer Installation #2 TempNote 5 Compensator Page Page Industrial Automation and Control