SM51 Unpacking & Assembly Instructions
Figure 5. Configuration for 2-3/4” and 3” bolts.
3.Bolt on the connecting beam (part 4 from Figure 2) using a 5/8” socket with extension and combination wrench, to the cells using two of the large 7/16” x 6” bolts, 7/16” washers, and 7/16” nuts (parts A, B, and C in HARDWARE section at end of these instructions), end cap washers and end caps (parts F and H in HARDWARE section). Figure 6 shows the connected cells. You will need to remove the pulleys from the teardrop pulley assemblies to gain clearance for the socket wrench extension. Leave the pulleys out of the housings until the cables have been installed.
7/16” x 6” (6)- mount on tops
T
U
Remove pulleys from housings to give clearance to socket extension
3/8” x 3” (2)- bolt top beams together
Figure 6. Bolt on the connecting beam, lat top, and tricep top.