American Dryer Corp MDG-30 installation manual This Pipe Size Requirement

Page 28

3.Piping Connections

ALL components/materials must conform to National Fuel Gas Code Specifications ANSI Z223.1-LATEST EDITION, or in Canada, CAN/CGA-B149.1-M91 (Natural Gas) or CAN/CGA-B149.2-M91 (Liquid Propane [L.P.] Gas) or LATEST EDITION (for General Installation and Gas Plumbing), as well as local codes and ordinances and must be done by a qualified professional. It is important that gas pressure regulators meet applicable pressure requirements, and that gas meters be rated for the total amount of ALL the appliance Btus being supplied.

The dryer is provided with a 1/2” N.P.T. inlet pipe connection located in the upper rear area of the dryer. The minimum pipe size (supply line) to the dryer is 1/2” N.P.T. For ease in servicing, the gas supply line of each dryer must have its own shutoff valve.

IMPORTANT: The gas supply line to each dryer must be a minimum of 1/2.” DO NOT REDUCE

THIS PIPE SIZE REQUIREMENT.

The size of the main gas supply line (header) will vary depending on the distance this line travels from the gas meter or, in the case of L.P. gas, the supply tank, other gas-operated appliances on the same line, etc. Specific information regarding supply line size should be determined by the gas supplier.

NOTE: Undersized gas supply piping can create a low or inconsistent pressure, which will result in erratic operation of the burner ignition system.

24

Image 28
Contents MDG-30 Coin Installation Manual Retain This Manual In a Safe Place For Future Reference Foryour Safety Page Table of Contents Section Procedure for Functional Check of Replacement Important Information Receiving and HandlingSafety Precautions What to do if YOU Smell GASPage Specifications SpecificationsSpecifications GAS only Installation Procedures Unpacking and Setting UPLocation Requirements Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements Single Dryer Venting Vertical Venting Multiple Dryer Common Venting Illus. D Importantventingreminders Electrical Information Electrical RequirementsMust be Provided Single-Phase 1ø Electrical Connections Leads GAS 120GAS Information Rating Kcal/hr22,680 This Pipe Size Requirement Page Preparation for Operation and START-UP Preoperational Tests Preoperational Instructions Basket Tumbler CoatingPage Select Temperature Shutdown Instructions Service SERVICE/PARTS InformationParts Returning Warranty Cards Warranty InformationWarranty Cleaning Routine MaintenanceSuggested Cleaning Schedule Adjustments LubricationNo light emitting diode L.E.D. display TroubleshootingDrive motor is not operating does not start Blower motor is not operating does not start Microprocessor controller computer display reads dSFLMicroprocessor controller computer display reads door No heat, ignitor sparks, burner goes on and off right awayDryer operates but is taking too long to dry Dryer is making scraping noise at basket tumbler area Condensation on main door glassExcessive noise or vibration Main burners are burning with a yellow flame Heating unit is not operating all temperature selectionsDryer operates but is taking too long to dry load Dryer is cycling on hi-limit thermostat Datalabel Information Data LabelSerial Number Procedure for Functional Check Replacement Components Page Page Burner Manual Reset HI-LIMIT Instructions 12/15/99-150