D. FRESH AIR SUPPLY REQUIREMENTS

The air supply (make-up air) must be given careful consideration to assure proper performance of each dryer. An unrestricted source of air is necessary for each dryer. As a general rule, an unrestricted air entrance from the outdoors (atmosphere) of a minimum of 1-1/2 square feet (0.14 square meters) is required for each dryer. If registers or louvers are installed over the openings, then the area must be increased. It is not necessary to have a separate make-up air opening for each dryer. Common make-up air openings are acceptable. However, they must be set up in such a manner that the make-up air is distributed equally to the dryers. The dryer must be installed with provisions for adequate combustion and make-up air supply.

EXAMPLE: For a bank of eight (8) dryers, two (2) unrestricted openings measuring 2 feet by 3 feet (0.61 meters by 0.91 meters) 6 square feet [0.55 square meters] each opening) are acceptable.

IMPORTANT: Make-up air openings should not be located in an area directly near where exhaust vents exit the building.

Allowances must be made for remote or constricting passageways or where dryers are located at excessive altitudes or predominantly low pressure areas.

IMPORTANT: Make-up air must be provided from a source free of dry cleaning solvent fumes. Make-up air that is contaminated by dry cleaning solvent fumes will result in irreparable damage to the motors and other dryer components.

NOTE: Component failure due to dry cleaning solvent fumes will VOID THE WARRANTY.

11

Image 15
Contents MDG-30 Coin Installation Manual Retain This Manual In a Safe Place For Future Reference Foryour Safety Page Table of Contents Section Procedure for Functional Check of Replacement Receiving and Handling Important InformationWhat to do if YOU Smell GAS Safety PrecautionsPage Specifications SpecificationsSpecifications GAS only Unpacking and Setting UP Installation ProceduresLocation Requirements Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements Single Dryer Venting Vertical Venting Multiple Dryer Common Venting Illus. D Importantventingreminders Electrical Requirements Electrical InformationMust be Provided Single-Phase 1ø Electrical Connections Leads 120 GASGAS Information Kcal/hr Rating22,680 This Pipe Size Requirement Page Preparation for Operation and START-UP Preoperational Tests Basket Tumbler Coating Preoperational InstructionsPage Select Temperature Shutdown Instructions SERVICE/PARTS Information ServiceParts Warranty Information Returning Warranty CardsWarranty Routine Maintenance CleaningSuggested Cleaning Schedule Lubrication AdjustmentsTroubleshooting No light emitting diode L.E.D. displayDrive motor is not operating does not start Microprocessor controller computer display reads dSFL Blower motor is not operating does not startNo heat, ignitor sparks, burner goes on and off right away Microprocessor controller computer display reads doorDryer operates but is taking too long to dry Condensation on main door glass Dryer is making scraping noise at basket tumbler areaExcessive noise or vibration Heating unit is not operating all temperature selections Main burners are burning with a yellow flameDryer operates but is taking too long to dry load Dryer is cycling on hi-limit thermostat Data Label Datalabel InformationSerial Number Procedure for Functional Check Replacement Components Page Page Burner Manual Reset HI-LIMIT Instructions 12/15/99-150