Consistent gas pressure is essential at ALL gas connections. It is recommended that a 3/4-inch (19.05

mm)pipe gas loop be installed in the supply line servicing a bank of dryers. An in-line pressure regulator must be installed in the gas supply line (header) if the (natural) gas pressure exceeds 12.0 inches (29.9 mb) of water column (W.C.) pressure. Refer to the illustrations on the previous page.

NOTE: A water column test pressure of 3.5 inches (8.7 mb) for natural gas and 10.5 inches (26.1 mb) for liquid propane (L.P.) dryers is required at the gas valve pressure tap of each dryer for proper and safe operation.

A 1/8” N.P.T. plugged tap, accessible for a test gauge connection, must be installed in the main gas supply line immediately upstream of each dryer.

IMPORTANT: Pipe joint compounds that resist the action of natural gas and L.P. gas must be used.

IMPORTANT: Test ALL connections for leaks by brushing on a soapy water solution (liquid detergent works well).

WARNING: NEVER TEST FOR LEAKS WITH A FLAME!!!

ALL components/materials must conform to National Fuel Gas Code Specifications ANSI Z223.1-LATEST EDITION, or in Canada, CAN/CGA-B149.1-M91 (Natural Gas) or CAN/CGA-B149.2-M91 (L.P. Gas) or LATEST EDITION (for General Installation and Gas Plumbing), as well as local codes and ordinances and must be done by a qualified professional. It is important that gas pressure regulators meet applicable pressure requirements, and that gas meters be rated for the total amount of ALL the appliance Btus being supplied.

IMPORTANT: The dryer and its individual shutoff valve must be disconnected from the gas supply piping system during any pressure testing of that system at test pressures in excess of 1/2 psig (3.5 kPa).

NOTE: The dryer must be isolated from the gas supply piping system by closing its individual manual shutoff valve during any pressure test of the gas supply system at test pressures equal to or less than 1/2 psig (3.5 kPa).

25

Image 29
Contents MDG-30 Coin Installation Manual Retain This Manual In a Safe Place For Future Reference Foryour Safety Page Table of Contents Section Procedure for Functional Check of Replacement Receiving and Handling Important InformationWhat to do if YOU Smell GAS Safety PrecautionsPage Specifications SpecificationsSpecifications GAS only Unpacking and Setting UP Installation ProceduresLocation Requirements Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements Single Dryer Venting Vertical Venting Multiple Dryer Common Venting Illus. D Importantventingreminders Electrical Requirements Electrical InformationMust be Provided Single-Phase 1ø Electrical Connections Leads 120 GASGAS Information 22,680 Kcal/hrRating This Pipe Size Requirement Page Preparation for Operation and START-UP Preoperational Tests Basket Tumbler Coating Preoperational InstructionsPage Select Temperature Shutdown Instructions Parts SERVICE/PARTS InformationService Warranty Warranty InformationReturning Warranty Cards Suggested Cleaning Schedule Routine MaintenanceCleaning Lubrication AdjustmentsDrive motor is not operating does not start TroubleshootingNo light emitting diode L.E.D. display Microprocessor controller computer display reads dSFL Blower motor is not operating does not startNo heat, ignitor sparks, burner goes on and off right away Microprocessor controller computer display reads doorDryer operates but is taking too long to dry Excessive noise or vibration Condensation on main door glassDryer is making scraping noise at basket tumbler area Dryer operates but is taking too long to dry load Heating unit is not operating all temperature selectionsMain burners are burning with a yellow flame Dryer is cycling on hi-limit thermostat Data Label Datalabel InformationSerial Number Procedure for Functional Check Replacement Components Page Page Burner Manual Reset HI-LIMIT Instructions 12/15/99-150