Setup
3.In order to verify when lubricant is flowing and has reached the end of the lube line, loosen the connec- tor at the lube point of the line that is to be filled.
4.Stroke the hand pump until
5.Tighten the lube line connector at the lube point, but do not replace the port plugs or performance indica- tors into the ports on the front of the working sec- tion.
6.Repeat steps
NOTE: Do not replace any of the performance indicators or port plugs removed in Step 1 until the
Filling Master-to-Secondary Lube Lines
Refer to FIG. 4. when performing this procedure.
4.Continue to stroke the pump until the lubricant purges all the air out of the internal passages of the secondary divider valve and lubricant flows freely from all indicator ports with no evidence of included air.
5.Reinstall the port plugs or performance indicators in their respective positions in the secondary divider valve. Do not replace the port plugs or performance indicators in the master divider valve yet.
6.Repeat Steps
NOTE: Do not replace any of the performance indicators or port plugs removed in Step 1 from the master divider valve assembly until the
LUBE POINT
SECONDARY BLEED
MASTERTHROUGH
ALL PORTS
REMOVE INDICATOR
OR PORT PLUG
HAND PUMP | TI11099 |
FIG. 4
1.Remove the port plugs or performance indicators from all the indicator ports on the front of the master divider valve.
2.Connect a hand pump filled with clean, filtered lubri- cant to the indicator port closest to the lube output port that is feeding the line to the secondary divider valve.
3.Stroke the hand pump to fill the line between the master divider valve and secondary divider valve.
312497G | 5 |