BURNERFLAME
BURNER
MANIFOLD
C99021
Fig. 21 - Monoport Burner
LIMIT SWITCHES
Normally closed limit switch (LS) completes the control circuit.
Should the
allowable temperature, the limit switch opens and the control
circuit "breaks." Any interruption in the control circuit instantly
closes the gas valve and stops gas flow to the burners and pilot.
The blower motor continues to run until LS resets. The furnace board STATUS LED will display STATUS CODE 33.
When the air temperature at the limit switch drops to the
completes the control circuit. The
ROLLOUT SWITCH
The function of the rollout switch is to close the main gas valve in the event of flame rollout. The switch is located above the main
burners. When the temperature at the rollout switch reaches the
maximum allowable temperature, the control circuit trips, closing the gas valve and stopping gas flow to the burners. The indoor fan
motor (IFM) continues to run until switch is reset. The furnace board STATUS LED will display STATUS CODE 33.
CONTINUOUS FAN MODE
When continuous fan operation is requested by the UI indoor fan
motor will operate at continuous blower airflow. Continuous fan
operation is programmable. See the UI Owner's Manual for
detailed instructions. Terminal
During a call for gas heat, the Infinity control will transition the
indoor fan motor to continuous blower airflow or gas heat airflow,
whichever is lowest. The indoor fan motor will remain ON until
the burners ignite, then shut OFF and remain OFF for the
quickly, then restarts at the end of the
The indoor fan motor will revert to
When the UI "calls for cooling", the indoor fan motor will switch to operate at cooling airflow. When the call for cooling is satisfied,
the indoor fan motor will operate an additional 90 seconds at
cooling airflow before transitioning back to
When the call for continuous fan is removed, the indoor blower
will continue operating for an additional 5 seconds before shutting down, if no other function requires blower motor operation.
COMPONENT TEST
The Infinity Furnace Board features a gas component test system to
help diagnose a system problem in the case of a gas component
failure. To initiate the component test procedure, ensure that there
are no UI inputs to the control (the ABCD connector can be
removed from the Infinity control board for this operation) and all time delays have expired. Turn on setup switch
NOTE: The component test feature will not operate if the control is receiving any UI signals or until all time delays have expired.
The component test sequence is as follows:
1.The control turns the inducer motor ON and keeps it ON through step 3.
2.After waiting 10 seconds, the control turns the igniter ON for 15 seconds, then OFF.
3.The control then turns the indoor fan motor on for 15 seconds, then OFF.
4.After shutting the blower motor OFF, the control runs the inducer for 10 seconds, then turns it OFF.
NOTE: | The | EAC | terminals | are energized | when | the | blower | is | |||
operating. |
|
|
|
|
|
|
|
|
|
|
|
After the | component | test is completed, | one | or | more | status | codes | ||||
(11, 25, | or 41) | will flash. See | component | test | section | or | Status | ||||
Code Label for explanation of status codes. |
|
|
|
|
|
| |||||
NOTE: | To repeat | component | test, | turn setup | switch | to | |||||
OFF and then back ON. |
|
|
|
|
|
|
|
|
Check for Refrigerant Leaks
Locate and repair refrigerant leaks and charge the unit as follows:
1. Use both high- and
pressure and reclaim remaining refrigerant.
2. Repair leak following accepted practices.
NOTE: Install a filter drier whenever the system has been opened for repair.
3.Check system for leaks using an approved method.
4.Evacuate refrigerant system and reclaim refrigerant if no
additional leaks are found.
5.Charge unit with Puron
Start-Up Adjustments
Complete the required procedures given in the
when the outdoor temperature is below 40°F (4°C) (unless
the compressor. Allow 5 min. between "on" cycles to prevent
compressor damage.
CHECKING COOLING AND HEATING CONTROL OPERATION
See UI Installation Instructions for detailed system CHECKOUT.
CHECKING AND ADJUSTING REFRIGERANT CHARGE
The refrigerant system is fully charged with Puron
refrigerant and is tested and factory sealed.
NOTE: Any adjustment to refrigerant charge must be done with unit operating in HIGH stage.
NOTE: Adjustment of the refrigerant charge is not required
unless the unit is suspected of not having the proper
charge. The charging label and the tables shown refer to system
temperatures and pressures in cooling mode only. A refrigerant charging label is attached to the outside of the unit.
25