Carrier 50HQP072-120 specifications Pre-Start-Up

Page 16

PRE-START-UP

System Checkout — When the installation is complete, follow the system checkout procedure outlined below before starting up the system. Be sure:

1.Voltage is within the utilization range specifications of the unit compressor and fan motor and voltage is balanced for 3-phase units.

2.Fuses, breakers and wire are correct size.

3.Low voltage wiring is complete.

4.Piping and system flushing is complete.

5.Air is purged from closed loop system.

6.System is balanced as required. Monitor if necessary.

7.Isolation valves are open.

8.Water control valves or loop pumps are wired.

9.Condensate line is open and correctly pitched.

10.Transformer switched to lower voltage tap if necessary.

11.Blower rotates freely — shipping support is removed.

12.Blower speed is on correct setting.

13.Air filter is clean and in position.

14.Service/access panels are in place.

15.Return-air temperature is 4.4 to 26.7 C for heating and 10.0 to 43.3 C for cooling.

16.Air coil is clean.

17.Control field selected settings are correct.

AIR COIL — To obtain maximum performance, the air coil should be cleaned before starting the unit. A ten percent solution of dishwasher detergent and water is recommended for both sides of the coil. Rinse thoroughly with water.

Airflow and External Static Pressure — The 50HQP units are available with standard, low, and high-staticfactory-installed options. These options will substitute a differ- ent blower drive sheave for each static range. In addition, cer- tain static ranges may require the optional large fan motor.

SHEAVE ADJUSTMENT — The 50HQP units are supplied with a variable sheave drive on the fan motor to adjust for dif- fering airflows at various ESP (external static pressure) condi- tions. See Tables 5-7 for unit airflows. When fully closed, the sheave will produce the highest static capability (higher rpm).

To adjust sheave position, follow the procedure outlined below:

1.Loosen belt tension and remove belt.

2.Loosen set screw on fan motor.

3.Open sheave to desired position.

4.Retighten set screw and replace belt. NOTE: Set belt tension as outlined below.

BELT TENSION ADJUSTMENT — An overly loose belt will, upon starting motor, produce a slippage “squeal” and cause premature belt failure and or intermittent airflow. An overly tight belt can cause premature motor or blower bear- ing failure. To adjust the belt tension, follow the procedure outlined below:

1.Remove belt from motor sheave.

2.Lift motor assembly.

3.Loosen the 5/16-in. hex nuts on the grommet motor adjust- ment bolts (2 per bolt). To increase the belt tension loosen the top hex nut. To decrease the belt tension loosen the bottom hex nut.

4.Turn the bolts by hand to the desired position then tighten the 5/16-in. hex nuts (2 per bolt).

5.Lower the motor assembly.

6.Install the belt.

7.The belt tension can be adjusted by using one of the fol- lowing methods:

a.Tighten until belt deflects approximately 13 mm with very firm finger pressure.

b.Grasp belt midway between two pulleys and twist for a 90-degree rotation.

NOTE: Adjusting less than 90 degrees will over- tighten the belt and adjusting more than 90 degrees will loosen belt.

c.Set proper belt tension to 32 to 36 kg.

NOTE: The motor position should not need adjustment. Motor sheave position is at mid position of each sheave. For example, the motor sheave is 2.5 turns open on a 5-turn sheave. The belt tension adjustment can also be accomplished by turning the 5/16-in. hex nuts to the desired position.

NOTE: Available airflows for all units are shown in Tables 5-7.

16

Image 16
Contents Contents Safety ConsiderationsInstallation GeneralPhysical Data 50HQP072-120 Units Unit Dimensions Typical Horizontal Installation Install Condensate Piping Drain Hanger BracketsRemoving Panels Install Field Power Supply Wiring Supply/Return Hose KitTypical Ground-Water Piping Installation Water Quality Guidelines MaterialDPP FP1FP2 HpwrSee legend and notes on SAT LWTSPT Electrical Data 50HQP072-120 Standard Units Electrical Data 50HQP072-120 Dual Point Power UnitsLow Voltage VA Ratings Install Field Control Wiring Jumper LocationsPRE-START-UP Blower Data 50HQP072 AirflowBlower Data 50HQP096 Blower Data 50HQP120 Deluxe D Control Jumper Settings See Fig Complete C Control Jumper Settings See FigField Selectable Inputs DIP Switch Block S2 Accessory 1 Relay Options DIP Switch Block S2 Accessory 2 Relay OptionsAccessory DIP Switch Position Relay Options OADUnit Start-Up in Cooling Mode START-UPOperating Limits Start Up SystemCoaxial Water Pressure Drop Unit Start-Up in Heating ModeSize Approximate Fluid Volume L Per 30 M of Pipe Antifreeze Percentages by VolumeOperation Units with Aquazone Complete C ControlSystem Test Aquazone Deluxe D Control LED IndicaFault Descriptions ServiceComplete C Control LED Code Gravity Flow Method a50-8586 Refrigerant Charging Air Coil Fan Motor RemovalSheave Alignment Unit Size Component Drive Package 50HQPTroubleshooting Thermistor Nominal ResistanceTroubleshooting Fault Heating Cooling Possible Cause SolutionUnit Does Not Operate Page Copyright 2010 Carrier Corporation START-UP Checklist II. START-UPHeating Cycle Analysis Cooling Cycle Analysis