Carrier 50HQP072-120 specifications Install Condensate Piping Drain, Hanger Brackets

Page 6

EXISTING DUCT SYSTEM — If the unit is connected to existing ductwork, consider the following:

Verify that the existing ducts have the proper capacity to handle the unit airflow. If the ductwork is too small, larger ductwork should be installed.

Check existing ductwork for leaks and repair as necessary.

NOTE: Local codes may require ventilation air to enter the space for proper indoor air quality. Hard-duct ventilation may be required for the ventilating air supply. If hard ducted venti- lation is not required, be sure that a proper air path is provided for ventilation air to unit to meet ventilation requirement of the space.

Step 6 — Install Condensate Piping Drain

INSTALLATION — Slope the unit toward the drain at a 1 cm per 50 cm pitch. See Fig. 4. If it is not possible to meet the required pitch, a condensate pump should be installed at the unit to pump condensate to building drain.

Install condensate trap at each unit with the top of the trap positioned below the unit condensate drain connection as shown in Fig. 5. Design the depth of the trap (water-seal) based upon the amount of ESP (external static pressure) capability of the blower (where 2 in. wg of ESP capability requires 2 in. of trap depth). As a general rule, 38 mm trap depth is the mini- mum. Each unit must be installed with its own individual trap and connection to the condensate line (main) or riser.

Units are not internally trapped, therefore an external trap is necessary. Each unit must be installed with its own individual trap and means to flush or blowout the condensate drain line. Do not install units with a common trap or vent. For typical condensate connections see Fig. 5.

NOTE: Never use a pipe size smaller than the connection.

VENTING — A vent should be installed in the condensate line of any application which may allow dirt or air to collect in the line. Consider the following:

Always install a vent where an application requires a long horizontal run.

Always install a vent where large units are working against higher external static pressure and to allow proper drainage for multiple units connected to the same condensate main.

Be sure to support the line where anticipated sagging from the condensate or when “double trapping” may occur.

If condensate pump is present on unit, be sure drain con- nections have a check valve to prevent back flow of con- densate into other units.

3/8" [10MM] THREADED

ROD (FIELD SUPPLIED)

VIBRATION ISOLATOR (FACTORY SUPPLIED)

WASHER (FIELD SUPPLIED)

DOUBLE HEX NUTS

(FIELD SUPPLIED)

a50-6260e8535

Fig. 3 — Hanger Brackets

1/4” Pitch for Drainage

Pitch Toward

Drain

a50-6260ef8536

Drain Connection

 

Fig. 4 — Horizontal Unit Pitch

 

Vent

*3/4" IPT

 

Trap Depth

Min 1.5"

1.5" [38mm]

[38mm]

3/4" PVC or

1/4" per foot

Copper by others

(21mm per m)

a50-6260e8537

drain slope

Fig. 5 — Trap Condensate Drain

Step 7 — Field Convert Air Discharge — Hori- zontal units can be field converted between straight (side) and back (end) discharge.

NOTE: It is not possible to field convert return air between left or right return models due to the necessity of refrigeration cop- per piping changes.

Field conversion must be completed on the ground. If the unit is already hung it should be taken down for the field con- version. Place in a well-lighted area. Conversion should only be attempted by a qualified service technician.

SIDE TO BACK DISCHARGE CONVERSION

1.Remove back panel and side access panel. See Fig. 6.

2.Loosen 2 motor slide nuts, raise motor slide assembly and remove belt and motor sheave. See Fig. 7.

3.Remove blower sheave. Remove motor bolts and careful- ly remove motor. See Fig. 8.

4.Remove 2 motor clips and reattach to opposite side. See Fig. 9.

5.Unbolt (3 per side) complete housing assembly. See Fig. 9.

6.Rotate complete assembly into new position. Locate over mounting holes in base, reattach using 3 bolts per side.

6

Image 6
Contents Contents Safety ConsiderationsInstallation GeneralPhysical Data 50HQP072-120 Units Unit Dimensions Typical Horizontal Installation Install Condensate Piping Drain Hanger BracketsRemoving Panels Install Field Power Supply Wiring Supply/Return Hose KitTypical Ground-Water Piping Installation Water Quality Guidelines MaterialFP2 DPPFP1 HpwrSee legend and notes on LWT SATSPT Electrical Data 50HQP072-120 Dual Point Power Units Electrical Data 50HQP072-120 Standard UnitsLow Voltage VA Ratings Install Field Control Wiring Jumper LocationsPRE-START-UP Blower Data 50HQP072 AirflowBlower Data 50HQP096 Blower Data 50HQP120 Complete C Control Jumper Settings See Fig Deluxe D Control Jumper Settings See FigField Selectable Inputs Accessory DIP Switch Position Relay Options DIP Switch Block S2 Accessory 1 Relay OptionsDIP Switch Block S2 Accessory 2 Relay Options OADOperating Limits Unit Start-Up in Cooling ModeSTART-UP Start Up SystemUnit Start-Up in Heating Mode Coaxial Water Pressure DropSize Operation Approximate Fluid Volume L Per 30 M of PipeAntifreeze Percentages by Volume Units with Aquazone Complete C ControlSystem Test Aquazone Deluxe D Control LED IndicaService Fault DescriptionsComplete C Control LED Code Gravity Flow Method a50-8586 Refrigerant Charging Air Coil Fan Motor RemovalSheave Alignment Unit Size Component Drive Package 50HQPTroubleshooting Thermistor Nominal ResistanceTroubleshooting Fault Heating Cooling Possible Cause SolutionUnit Does Not Operate Page Copyright 2010 Carrier Corporation START-UP Checklist II. START-UPHeating Cycle Analysis Cooling Cycle Analysis