Checkout Procedure

All installations and services must be performed by qualified service personnel.

This furnace is designed not to require any burner adjustment. Burner aeration is fixed in this design. Burner flames can be seen by looking through the sight glass located on the burner box. Burner flames should be well-defined, light to medium blue in color, and almost transparent. (refer to Figure 24).

Figure 24: Sketch of Typical Main Burner Flames During Operation

NOTICE: When operating on propane gas, it is not unusual for flames to have yellow or orange colored tips.

If combustion problems are evident, it may indicate problems with either the furnace air supply or the vent system. Refer to the installation and maintenance sections of this manual, or contact Thermo Products at (574) 896-2133.

Checkout Procedure

1.Confirm the furnace exhaust vent and combustion air intake are constructed as outlined in the installation and service manual. They must not be blocked or otherwise obstructed.

2.Place system in operation and observe at least one (1) complete cycle to ensure all controls are operating properly. The main burner must light reliably under all conditions.

3.Perform gas leakage test on all gas pipe connections and pressure tap plugs.

45

Image 51
Contents INSTALLATION AND OPERATION MANUAL MODELS FOR USE WITH NATURAL GAS OR LP GAS PROPANECHX3-75N CDX3-75N CHX3-100N CDX3-100N CHX3-125N CDX3-125NI. SAFETY INFORMATION This and the previous page contain reproductions of the various warning and instruction labels placed on the Thermo Pride Two Stage Condensing Gas Furnaces. Please read and comply with the contents of these labels 1.A windows be opened The CHX3/CDX3 furnace models are sealed combustion design, which does not require an air shutter adjustment air shutters are not used for proper flame characteristics. Burner box access cover must always be secured with all screws in place and tightened before operating furnace INDEX SECTIONBEGINNING PAGE II. FURNACE SPECIFICATIONS CDX3 SERIES INSTALLATION PARTS PACKAGES – CHX3-75 INSTALLATION PARTS PACKAGES – CDX3-75 Grounding instructions III. GENERAL INSTALLATION B1. CDX3 HORIZONTAL APPLICATION B. FURNACE LOCATIONFigure PVC Pipe Designation Maximum Quantity of Elbows Outside Combustion Air Intake RH view E.Direct Venting Through a Sidewallc.The vent terminal shall not be located •near soffit vents, crawl space vents, or other areas where condensate or water vapor could create a nuisance, hazard, or cause property damage, and Page E1. Single-PipeSidewall Venting Option 5.Optional Direct Vent Terminations Install these optional kits according to the instructions provided with each kit. The location and clearance requirements are identical to those of the standard vent terminations described in this manual 1.Figures 6B, 7, and 8 follow depicting typical exhaust vent and air intake connections for the furnace model series CHX3 and the CDX3, respectively, as well as a list of required parts to correctly install each system Applications Applications leading away from the furnace must be composed of 3-inchdiameter PVC pipe and pipe fittings only. Refer to item E in Figure 3. Connecting The Combustion Air Intake Piping Figure 14. TRAP ASSEMBLY MOUNTED ON CHX3 I.CONDENSATE DRAIN LINE AND TRAP ASSEMBLYFigure 15. TRAP ASSEMBLY MOUNTED ON CDX3 2.Determine on which side of furnace the condensate disposal line is to be run NOTICE: On CHX3/CDX3’s this must be the same side as the flue outlet or bottom of unit. Attach the condensate trap to the furnace casing using the #8x3/4” sheet metal screws provided in the parts package. Pilot holes are provided on both sides of the casing for mounting J. GENERAL GAS PIPING J1. REQUIREMENTS AND SIZING OF DUCT WORK Figure 18A TABLE 2A K. FILTERS 1. CHX3 MODELS: HIGHBOYS Figure2. CDX3 MODELS: COUNTERFLOWS Figure L. WIRING Table 4A Time S7 DIP SwitchSwitch Settings Options2-StageBlower Settings from factory Table 4C IV. STARTING THE UNIT A. SEQUENCE OF OPERATIONS FLAME MUST BE DETECTED IF THERMOSTAT W2 CONTACTS ARE CLOSED OTHERWISE OPERATING INSTRUCTIONS B. INITIAL START UPB.Gas flowrate by clocking gas meter C. Measuring And Adjusting Heat Input RateObserve the following precautions when measuring A.Burner manifold pressure with a pressure gaugeNOTICE: A U-tubemanometer, measuring pressure in inches of water column, is recommended for all gas pressure measurements. However, an aneroid pressure gauge, in good working condition, capable of reading pressure changes of 0.05 in. W.G., or less, that was recently calibrated within the last year, is a satisfactory alternate. These two 2 devices will be considered as equivalent and interchangeable. Either device is referred to below as a “pressure gauge” Heat input rate in BTUH = Figure Checking The Burner Flame 21.Go to Checkout Procedure belowCheckout Procedure TABLE 6 - CONVERTING GAS FLOW RATE V. INSTALLERS INSTRUCTIONS TO USER D. FURNACE CHECKOUT PROCEDUREFigure VI. TROUBLESHOOTING Power must be disconnected before servicing DIAGNOSTIC FEATURESTROUBLESHOOTING GUIDE IS INDUCER RUNNING ON LOW SPEED? YES DOES THE HOT DO BURNERS STAY LIT PAST PROOF OF FLAME CHECK? REPLACE THE 50V51-843CONTROL CHECK FOR 24 VOLTS Appendix –AReplacement Parts List Page Page Page Appendix – B Wiring Diagrams