Thermo Products 125n, chx-3 75n D. Furnace Checkout Procedure, V. Installers Instructions To User

Page 53

All installations and services must be performed by qualified service personnel.

D. FURNACE CHECKOUT PROCEDURE

Before any system of gas piping is finally put into service, it shall be carefully tested to assure that it is gas tight as indicated in the manual.

NOTICE: All controls on the unit should be checked for proper functioning prior to the qualified service personnel leaving the job site. Specifically the following should be checked:

With furnace in normal heating operation, check to make certain blower will start and stop automatically under control of integrated fan control.

1.Check safety limit control as follows:

a.Shut off incoming power.

b.Disconnect blower motor leads.

c.Restore power to furnace.

d.Set thermostat above room temperature calling for heat.

e.When temperatures are reached in furnace at limit control setting with blower out of operation, burner should shut off.

f.Shut off electrical power.

IMPORTANT: Remove blockage or reconnect blower motor and restore power.

2.Make certain thermostat will automatically start and stop furnace.

3.Block the flue pipe gradually with a flat piece of metal, until the pressure switch functions shutting off the main burners. Note: If the burner was initially operating in high fire, the burner will first reduce rate to the low fire setting. As the flue becomes more blocked, the pressure switch will function and completely shut off the main burners.

4.Block the PVC pipe inlet gradually with a flat piece of metal until pressure switch functions shutting off the main burners. Note: If the burner was initially operating in high fire, the burner will first reduce rate to the low fire setting. As the flue becomes more blocked, the pressure switch will function and completely shut off the main burners.

IMPORTANT: Remove flue air inlet blockage when done.

5.Remove the blower compartment access door with the furnace operating. The door interrupt switch is in the 120 volt circuit and will shut down the entire system. Replace the blower door and the furnace start-up cycle will begin.

V. INSTALLER'S INSTRUCTIONS TO USER:

After completing the installation, the installer shall inform and/or demonstrate to the homeowner:

1.The location of all the instructions in the furnace and that these instructions and the users information manual must be kept along with instructions for any accessories in the plastic pouch on the inside of the furnace.

2.The location and use of the manual gas shut off valve and furnace electrical disconnect switch. Instruct user to always shut off gas before shutting off electric power.

3.The sequence of operation of the furnace.

4.The correct operation and maintenance of the appliance as outlined in the users information manual.

47

Image 53
Contents CHX3-75N CDX3-75N CHX3-100N CDX3-100N MODELS FOR USE WITH NATURAL GAS OR LP GAS PROPANECHX3-125N CDX3-125N INSTALLATION AND OPERATION MANUALI. SAFETY INFORMATION This and the previous page contain reproductions of the various warning and instruction labels placed on the Thermo Pride Two Stage Condensing Gas Furnaces. Please read and comply with the contents of these labels 1.A windows be opened The CHX3/CDX3 furnace models are sealed combustion design, which does not require an air shutter adjustment air shutters are not used for proper flame characteristics. Burner box access cover must always be secured with all screws in place and tightened before operating furnace BEGINNING PAGE INDEXSECTION II. FURNACE SPECIFICATIONS CDX3 SERIES INSTALLATION PARTS PACKAGES – CHX3-75 INSTALLATION PARTS PACKAGES – CDX3-75 Grounding instructions III. GENERAL INSTALLATION B1. CDX3 HORIZONTAL APPLICATION B. FURNACE LOCATIONFigure PVC Pipe Designation Maximum Quantity of Elbows Outside Combustion Air Intake RH view E.Direct Venting Through a Sidewallc.The vent terminal shall not be located •near soffit vents, crawl space vents, or other areas where condensate or water vapor could create a nuisance, hazard, or cause property damage, and Page E1. Single-PipeSidewall Venting Option 5.Optional Direct Vent Terminations Install these optional kits according to the instructions provided with each kit. The location and clearance requirements are identical to those of the standard vent terminations described in this manual 1.Figures 6B, 7, and 8 follow depicting typical exhaust vent and air intake connections for the furnace model series CHX3 and the CDX3, respectively, as well as a list of required parts to correctly install each system Applications Applications leading away from the furnace must be composed of 3-inchdiameter PVC pipe and pipe fittings only. Refer to item E in Figure 3. Connecting The Combustion Air Intake Piping Figure 14. TRAP ASSEMBLY MOUNTED ON CHX3 I.CONDENSATE DRAIN LINE AND TRAP ASSEMBLYFigure 15. TRAP ASSEMBLY MOUNTED ON CDX3 2.Determine on which side of furnace the condensate disposal line is to be run NOTICE: On CHX3/CDX3’s this must be the same side as the flue outlet or bottom of unit. Attach the condensate trap to the furnace casing using the #8x3/4” sheet metal screws provided in the parts package. Pilot holes are provided on both sides of the casing for mounting J. GENERAL GAS PIPING J1. REQUIREMENTS AND SIZING OF DUCT WORK Figure 18A TABLE 2A 2. CDX3 MODELS: COUNTERFLOWS K. FILTERS 1. CHX3 MODELS: HIGHBOYSFigure Figure L. WIRING Table 4A Switch Settings S7 DIP SwitchOptions Time2-StageBlower Settings from factory Table 4C IV. STARTING THE UNIT A. SEQUENCE OF OPERATIONS FLAME MUST BE DETECTED IF THERMOSTAT W2 CONTACTS ARE CLOSED OTHERWISE OPERATING INSTRUCTIONS B. INITIAL START UPObserve the following precautions when measuring C. Measuring And Adjusting Heat Input RateA.Burner manifold pressure with a pressure gauge B.Gas flowrate by clocking gas meterNOTICE: A U-tubemanometer, measuring pressure in inches of water column, is recommended for all gas pressure measurements. However, an aneroid pressure gauge, in good working condition, capable of reading pressure changes of 0.05 in. W.G., or less, that was recently calibrated within the last year, is a satisfactory alternate. These two 2 devices will be considered as equivalent and interchangeable. Either device is referred to below as a “pressure gauge” Heat input rate in BTUH = Figure Checking The Burner Flame 21.Go to Checkout Procedure belowCheckout Procedure TABLE 6 - CONVERTING GAS FLOW RATE V. INSTALLERS INSTRUCTIONS TO USER D. FURNACE CHECKOUT PROCEDUREFigure VI. TROUBLESHOOTING Power must be disconnected before servicing DIAGNOSTIC FEATURESTROUBLESHOOTING GUIDE IS INDUCER RUNNING ON LOW SPEED? YES DOES THE HOT DO BURNERS STAY LIT PAST PROOF OF FLAME CHECK? REPLACE THE 50V51-843CONTROL CHECK FOR 24 VOLTS Appendix –AReplacement Parts List Page Page Page Appendix – B Wiring Diagrams