FIG. 12 |
FIG. 13 |
BOILER PUMP OPERATION
In certain modes of operation, the control can operate the individual boiler pumps on each boiler in addition to the pri- mary pump. The boiler pump turns on prior to the boiler fir- ing and continues to run after the boiler is turned off. The amount of time that the boiler pump turns on prior to the boiler firing is determined by the BOIL MASS setting. If a BOIL MASS of Lo is selected, the boiler pump turns on 15 seconds prior to the boiler. If a BOIL MASS of Medium is selected, the boiler pump turns on 22 seconds prior to the boiler. If a BOIL MASS of Hi is selected, the boiler pump turns on 30 seconds prior to the boiler. However, if the con- trol is operating based on a set point demand, the boiler pump turns on 5 seconds prior to the boiler, see Figure 13.
Boiler Pump Purge
FIG. 14 |
The amount of time that the boiler pump continues to run after the boiler turns off is adjustable using the boiler pump purge setting (PURG Boil Pmp).
SECTION D: BOILER RESET OPERATION
SECTION D1: BOILER RESET (STAND ALONE)
BOILER DEMAND
When operating in the
9
BOILER TARGET TEMPERATURE
The boiler target temperature is determined from the char- acterized heating curve settings and the outdoor air tem- perature. The control displays the temperature that it is cur- rently trying to maintain as the boiler supply temperature. If the control does not presently have a requirement for heat, it does not show a boiler target temperature. Instead, "- -
CHARACTERIZED HEATING CURVE
The control varies the supply water temperature based on the outdoor air temperature. The control takes into account the type of terminal unit that the system is using. Since dif- ferent types of terminal units transfer heat to a space using different proportions of radiation, natural convection and forced convection, the supply water temperature must be controlled differently. Once a terminal unit is selected, the control varies the supply water temperature according to the