TESTING THE CONTROL

The control has a built-in test routine that is used to test the main control functions. The control continually monitors the sensors and displays an error message whenever a fault is found. See the following pages for a list of the control’s error messages and possible causes. When the Test but- ton is pressed, the test light is turned on. The individual out- puts and relays are tested in the following test sequence.

FIG. 51

TEST SEQUENCE

Each step in the test sequence lasts 10 seconds.

During the test routine, if a demand from the system is pres- ent, the test sequence may be paused by pressing the Test button. If the Test button is not pressed again for 5 minutes while the test sequence is paused, the control exits the entire test routine. If the test sequence is paused, the Test button can be pressed again to advance to the next step. This can also be used to rapidly advance through the test sequence. To reach the desired step, repeatedly press and release the Test button until the appropriate device and seg- ment in the display turn on.

Step 1 The primary pump is turned on and remains on for the entire test routine.

Step 2 If the Alarm / C.A. DIP switch is set to Alarm, the Alarm contact is turned on for 10 seconds and then shuts off. If the Alarm / C.A. DIP switch is set to C.A, the com- bustion Air Damper contact is turned on and remains on for the entire test routine.

Step 3 For each boiler that is set to Auto, the following test sequence is used.

If the mode indicates that a boiler pump is used, the boiler pump is turned on and remains on.

Next, the first stage of the boiler is turned on and remains on.

If a second stage is present, the second stage is turned on and remains on.

If a third stage is present, the third stage is turned on and remains on. If a fourth stage is

present, the fourth stage is turned on.

After ten seconds, all stages and the boiler pump are turned off.

Step 4 If DHW MODE is set to 1 or 2 and the last boiler in modes 1, 4, and 5 are set to OFF, the primary pump is shut off and the DHW contact is closed.

Step 5 If DHW MODE is set to 3 or 4 and the last boiler in modes 1, 4, and 5 are set to OFF, the primary pump stays on and the DHW contact is closed.

Step 6 All contacts are turned off.

MAX HEAT

The control has a function called Max Heat, see Figure 52. In this mode, the control turns on and operates the system up to the maximum set temperatures as long as there is a demand for heat. The control continues to operate in this mode for up to 24 hours or until the Item, Menu or Test but- ton is pressed. This mode may be used for running all cir- culators during system start-up in order to purge air from the piping. To enable the Max Heat feature, use the following procedure.

1)Press and hold the Test button for more than 3 seconds. At this point, the control flashes the MAX segment and dis- plays the word OFF.

2)Using the up or down arrow buttons, select the word On. After 3 seconds, the control turns on all outputs. However, the max heat mode is still limited by the BOIL MAX setting.

3)To cancel the Max Heat mode, press the Item, Menu, or Test button.

4)Once the Max Heat mode has either ended or is can- celled, the control resumes normal operation.

FIG. 52

29

Image 29
Contents Additional Functions Include Installation InstructionsTable of Contents Display Section a General Operation Boiler Reset Stand AloneDomestic Hot Water Set PointBoiler Alarm AlarmCombustion Air C. a Fixed Lead RotationResetting the Running Times Resetting the Rotation SequenceSection B Staging Operation ModeLo / Lo Fire DelayLo / Hi Med Section C Pump OperationFixed Differential Auto DifferentialBoiler Pump Purge Section D Boiler Reset OperationType of terminal unit. This improves the control of the air High Mass Radiant DHW Demand Section E Domestic HOT Water OPERA- TionDHW Mode 4 DHW in Primary / Secondary with Priority Section F SET Point Operation Section G External Input Operation Setp Mode 1 Setpoint in ParallelDc or 4 20 mA Dc or 0 20 mAGeneral Ac PowerBoiler Demand DHW DemandSet Point Demand Combustion Air / Alarm Contact C.A./AlarmExternal Input 0 10 V dc Primary Pump Contact Prim P1Relay 9 / DHW UnOccupied SwitchBoiler Return Sensor Boiler Supply SensorExternal Input Primary Pump Prim P1 Combustion Air or Alarm C.A. / AlarmGeneral Cleaning the ControlRotate / OFF Page Page Page DHW Mode Stage DelayBoiler Minimum Boiler MaximumThis item is only available when DHW Mode is set to OFF Testing the Control Error Messages Is not a safety limit control Technical DataTypical Boiler Installation Typical Boiler Installation Typical DWH Priority Heating Package System