Lochinvar 497 - 2067 Check for gas leaks, Check thermostat circuits, Check vent and air piping

Page 47

6 Startup (continued)

Check for gas leaks

WARNING Before starting the boiler, and during initial operation, smell near the floor and around

the boiler for gas odorant or any unusual odor. Remove the front access panel and smell the interior of the boiler enclosure. Do not proceed with startup if there is any indication of a gas leak. Use an approved leak detection solution. Repair any leaks at once.

WARNING

Propane boilers only – Your propane supplier

 

mixes an odorant with the propane to make

 

 

its presence detectable. In some instances, the

 

odorant can fade, and the gas may no longer

 

have an odor. Before startup (and periodically

 

thereafter), have the propane supplier verify

 

the correct odorant level in the gas.

Check thermostat circuit(s)

1.Disconnect the two external wires connected to the enable terminals on the connection board.

2.Connect a voltmeter across these two incoming wires. Close each thermostat, zone valve, and relay in the external circuit one at a time and check the voltmeter reading across the incoming wires.

3.There should NEVER be a voltage reading.

4.If a voltage does occur under any condition, check and correct the external wiring. (This is a common problem when using 3-wire zone valves.)

5.Once the external thermostat circuit wiring is checked and corrected if necessary, reconnect the external thermostat circuit wires to the connection board. Allow the boiler to cycle.

Check vent and air piping

1.Inspect vent piping and air piping for signs of deterioration from corrosion, physical damage or sagging. Verify air piping and vent piping are intact and correctly installed per this manual.

Installation & Service Manual

Boiler operation

8.Verify that all adjustable points in the Operator Interface are set as required.

9.Boiler should begin the start-up process for the sequence of operation.

10.The boiler will ignite and operate to meet the system demand.

11.Ensure that inlet water temperature does not fall below the specified minimum for the boiler.

12.As system demand is satisfied, the burner will cycle off and the combustion air blower will run for a post purge operation before the boiler shuts down.

Start the boiler

1.Read and follow the Lighting Instructions in FIG. 6-1, on page 45.

If boiler does not start correctly

1.Check for loose connections, blown fuse or service switch off?

2.Is external limit control (if used) open? Is boiler water temperature above 200°F (93.3°C)?

3.Is thermostat set below room temperature?

4.Is gas turned on at meter or boiler?

5.Is incoming gas pressure less than 4 inches water column?

If none of the above corrects the problem, refer to the Maintenance Section of this manual.

WARNING The venting system must be installed so that it will prevent flue gas spillage and carbon

monoxide emissions, which will result in severe personal injury or death.

Placing the boiler in operation

Boiler operational checks

2.Turn the boiler main power switch to the “ON” position.

3.Confirm the settings of the temperature control.

4.Push the reset for the low water cutoff (if equipped).

5.Ensure that maximum flow to the boiler does not exceed 55 GPM on Models 402 - 752 and 90 GPM on Models 992 - 2072. Verify by checking temperature rise while burner is firing at 100% of rated input.

6.Install a manometer on the gas supply to the boiler and verify minimum gas supply pressure as the burner fires at 100% of rated input.

7.Verify operation of safeties as necessary (low water

cutoff, high limit, gas pressure, etc.,).

 

47

 

Image 47
Contents Save this manual for future reference What to do if YOU Smell GASContents Checking equipment WarrantyPlease read before proceeding Special instructionsCodes Safety informationOwner warning Prevention of freezingCopper-fin How it works Copper-fin How it works Models 987 2067 Front View Models 987 2067 Rear View Copper-fin =B=R Rating RatingsCopper-fin Specifications Indoor clearances from combustible construction InstallationDetermine unit location Locating the unitPump operation Outdoor boiler installationShut-down and draining Freeze protectionNumber Freeze Protection for a Heating Boiler System if requiredCombustion and Ventilation Air Minimum Recommended Combustion AIR Supply to Equipment RoomCombustion air filter 3Combustion air filter Models 497Outside Combustion Air, No Ducts Outside Combustion Air, Using DuctsCombustion Air Options Combustion Air from an Interior Space Exhaust FansVertical vent termination clearances and location VentingGeneral information Venting supportFlue Pipe Sizes Model Flue Size Vent system optionsBarometric damper location Common venting systems Conventional negative draft ventingNegative draft Flue outlet pipingInspection of a masonry chimney Masonry chimney installationOutdoor vent/air inlet location Outdoor installation ventingOutdoor Vent Kits Model Pump Cover Without Pump Cover Outdoor vent kitInlet GAS Pressure Natural Model Connecting to gas supply Gas pipingGas connections Gas pressure testFittings to Equivalent Straight Pipe Suggested GAS Pipe Size for Single Unit InstallationsGas connection Gas train and controlsChecking gas supply pressure GAS Piping Size ChartCombination gas valves Venting of combination gas valves3Measuring gas supply pressure at combination gas valve Gas manifold pressure adjustmentNat. Gas 4Measuring manifold gas pressureWater connections Boiler circulator requirements Pressure Drop ChartWater connections heating boilers only Run Cycle Output Minimum System Load Temp. Rise 8.33 60 Min Minimum boiler water temperaturesLow system water volume LTV Valve Kits Model LTV Valve KIT Low temperature return water systemsSystem Temperature Rise Chart Radiant floor and snow melt heating systemsCommon Manifold Size Min Models 987 Number of Units Common Manifold Size Min Models 497 Number of UnitsGPM Diameter6Primary/secondary piping of multiple boilers 7Boiler with low temperature bypass 8Primary/secondary piping with buffer tank General plumbing rules Installation with a chilled water systemTypical heating boiler installations Boiler flow rateWater treatment Temperature / pressure gaugeBoiler bypass requirements Filling the systemVAC Connecting to electrical supplyElectrical connections AMP Draw DataTerminal strip connection options BurnersOJ1 OJ2 Temperature adjustmentLocating the temperature control Temperature control settingsOutdoor reset option Boiler application Temperature control sensorsRemote sensor for pump delay Placement of sensorsHot surface igniter and ignition control module Remote Wire Connection Wire Gauge Max. Allowable LengthHot surface ignition system Remote mounting of a sensorIgnition and control timings Diagnostic Status IndicationSix Operation and diagnostic lightsSequence Constant Ignition Stage 2 onOFF StartupPurge air from water system Freeze protection when usedCheck/control water chemistry Fill and test water systemStart the boiler Check for gas leaksCheck thermostat circuits Check vent and air pipingMaximum Water Flow Domestic water heatersWater velocity control Initial set-up of maximum water flow1Typical water heater piping with storage tank 2Single water heater piping with two storage tanks Models 497 Number of Units Common Manifold Size Min4Multiple water heater piping with multiple storage tanks Water chemistry Required temperature risePipe Sizing Chart 497 987 Pipe size requirementsHeat exchanger Potable hot water temperature control settingsDomestic water temperature Minimum pump performanceLocation of cold water supply piping connections Cathodic protection High water temperature limit controlOptional relief valve Thermal expansionMaintenance Combustion and ventilation air Adjustment procedure Models 497 Overview Sequence of operationServicing a hot surface igniter and ignition module Ignition system checkoutEnd of sequence Heat transfer processGlossary Hi-Lo Fire Relay Pump Delay Electronic Thermostat FunctionTrial for Ignition Ignition Module Function Igniter Controlled by Ignition ModuleLadder diagram DiagramsDiagrams Connection diagram Connection diagram

497 - 2067 specifications

Lochinvar 497 - 2067 is a highly efficient and versatile condensing boiler that is designed to meet the diverse heating needs of residential and commercial applications. Known for its impressive performance and advanced technology, the Lochinvar 497 - 2067 has garnered a reputation as a reliable choice among heating professionals.

One of the standout features of the Lochinvar 497 - 2067 is its impressive thermal efficiency. The boiler boasts an efficiency rating of up to 95% AFUE (Annual Fuel Utilization Efficiency), allowing users to significantly reduce their energy costs while minimizing environmental impact. This efficiency is facilitated by its innovative condensing technology, which captures and reuses heat from exhaust gases for optimal performance.

The Lochinvar 497 - 2067 is equipped with a robust stainless steel heat exchanger designed to handle high temperatures and ensure long-lasting performance. The heat exchanger’s design maximizes heat transfer, while its corrosion-resistant properties guarantee durability over time. This contributes to the boiler's overall longevity and serviceability, reducing the need for frequent replacements.

Control is another critical feature of the Lochinvar 497 - 2067. The boiler comes with an advanced control system that enables easy management of system operations. Users can take advantage of features such as outdoor reset control, which adjusts the temperature of the boiler based on external weather conditions, enhancing system efficiency and comfort.

In terms of safety, the Lochinvar 497 - 2067 incorporates several cutting-edge safety features, including a flame detection system and multiple safety shut-off devices. These safeguards help to ensure the safe operation of the boiler, providing peace of mind to users and heating professionals alike.

Another important characteristic is the compact design of the Lochinvar 497 - 2067, which allows for flexible installation in various settings, including tight spaces. Its lightweight structure further simplifies the installation process, making it a practical choice for contractors.

In summary, the Lochinvar 497 - 2067 is an exceptional high-efficiency condensing boiler that combines advanced technology, durability, and ease of use. With its impressive thermal efficiency, superior heat exchanger design, advanced control systems, and enhanced safety measures, it stands out as a top choice for those seeking reliable heating solutions. This boiler not only meets but exceeds modern demands for energy efficiency and performance, solidifying its position in the market.