Lennox International Inc 506945-01 Electrical -- High Voltage and Field Control Wiring

Page 12

STEP 4 -- ELECTRICAL (CONTINUED) -- High Voltage and Field Control Wiring

The following illustration provide an example of control wiring connections when using standard thermostat.

ROUTING HIGH VOLTAGE, GROUND AND CONTROL WIRING

HIGH VOLTAGE / GROUND WIRES

FIELD CONTROL WIRING

Any excess high voltage field wiring should be trimmed and secured away from any low voltage field wiring. To facilitate a conduit, a cutout is located in the bottom of the control panel. Connect conduit to the control panel using a proper conduit fitting.

NOTE — Wire tie provides low voltage control wire strain relief and maintains separation of field-installed low and high voltage circuits.

NOTE — For proper voltages, select thermostat wire (control wires) gauge per table above.

NOTE — Do not bundle any excess 24VAC control wires inside control panel.

Install low voltage wiring from outdoor to indoor unit and from thermostat to indoor unit as illustrated.

ARun 24VAC control wires through hole with grommet and secure with provided wire tie.

THERMOSTAT

INDOOR UNIT

 

POWER

R

R

 

HEAT

W1

W

 

 

YELLOW

Y

COOLING

Y

 

G

INDOOR BLOWER

G

 

BLACK

 

COMMON

C

C

OUTDOOR UNIT

Y1

C

BMake 24VAC thermostat wire connections. Locate the two wires from the contactor and make connection using field-provided wire nuts:

S Yellow to Y1

S Black to C (common)

 

WIRE RUN LENGTH

AWG# INSULATION TYPE

 

 

LESS THAN 100' (30 METERS)

18

TEMPERATURE RATING

 

MORE THAN 100' (30 METERS)

16

35ºC MINIMUM.

STEP 5 -- UNIT START-UP

FIGURE 14

8.Recheck voltage while the unit is running. Power must be within range shown on the unit nameplate.

IMPORTANT

If unit is equipped with a crankcase heater, it should be energized 24 hours before unit start-up to prevent compressor damage as a result of slugging.

1.Rotate fan to check for binding.

2.Inspect all factory- and field-installed wiring for loose connections.

3.After evacuation is complete, open the liquid line and suction line service valve stems to release the refrigerant charge (contained in outdoor unit) into the system.

4.Replace the stem caps and tighten to the value listed in table 3.

5.Check voltage supply at the disconnect switch. The voltage must be within the range listed on the unit's nameplate. If not, do not start the equipment until you have consulted with the power company and the voltage condition has been corrected.

6.Connect manifold gauge set for testing and charging using figure NO TAG as a guideline.

7.Set the thermostat for a cooling demand. Turn on power to the indoor indoor unit and close the outdoor unit disconnect switch to start the unit.

9.Check system for sufficient refrigerate using the procedures outlined in under System Refrigerant.

OPERATING MANIFOLD GAUGE SET AND SERVICE VALVES

The liquid and vapor line service valves are used for removing refrigerant, flushing, leak testing, evacuating, checking charge and charging.

Each valve is equipped with a service port which has a factory-installed valve stem. Figure 15 provides information on how to access and operating both angle and ball service valves.

Torque Requirements

When servicing or repairing heating, ventilating, and air conditioning components, ensure the fasteners are appropriately tightened. Table 3 lists torque values for fasteners.

IMPORTANT

To prevent stripping of the various caps used, the appropriately sized wrench should be used and fitted snugly over the cap before tightening.

When servicing or repairing HVAC components, ensure the fasteners are appropriately tightened. Table 3 provides torque values for fasteners.

Page 12

Image 12
Contents Setting the Unit -- Clearances GeneralMinimum Clearance Between TWO Units Setting the Unit CONTIN­ UED -- Unit Placement Unit Dimensions Inches MMUnit Dimensions PlacementInstallation Refrigerant Line SET InstallingRefrigerant Line SET Installing Horizontal Runs Vertical Runs NEW Construction ShownLiquid Line Filter Drier Installation Typical Liquid Line Filter Drier InstallationRefrigerant Line SET Inches MM 2CONNECT Gauges and Equipment for Flushing Procedure Refrigerant Piping -- Brazing Procedures 1CUT and DeburWrap Service Valves Flow Nitrogen6BRAZE Line SET 7PREPARATION for Next StepRefrigerant Piping -- Installing Indoor Expansion Valve Indoor Expansion Valve InstallationSensing Bulb Installation Equalizer Line InstallationLeak Test and Evacuation Leak TestEvacuation Open both manifold valves and start the vacuum pumpElectrical -- Circuit Sizing and Wire Routing Size Circuit and Install Service Disconnect SwitchInstall Thermostat 24VAC TransformerElectrical -- High Voltage and Field Control Wiring Routing High VOLTAGE, Ground and Control WiringHigh Voltage / Ground Wires Field Control Wiring Operating Manifold Gauge SET and Service ValvesTorque Requirements Checking and Adding System Refrigerant Homeowners Information13ACX Start-Up and Performance Checklist Cooling ModeStart UP Checks