B.Deburring

Useaknife,plasticpipedeburringtool,orfiletoremoveburrsfromtheend ofsmalldiameterpipe. Besuretoremoveallburrsfromaroundtheinside as well as the outside of the pipe. Aslight chamfer (bevel) of about 10°- 15° should be added to the end to permit easier insertion of the pipe into the end of the fitting. Failure to chamfer the edge of the pipe may remove cement from the fitting socket, causing the joint to leak.

STEPB

C.Test dry fit of the joint

Tapered fitting sockets are designed so that an interfaced fit should occur when the pipe is inserted about 1/3 to 2/3 of the way into the socket. Occasionally, when pipe fitting dimensions are at the tolerance extremes, it will be possible to fully insert dry pipe to the bottom of the fitting socket. When this happens, a sufficient quantity of cement must be applied to the joint to fill the gap between the pipe and fitting. The gap must be filled to obtain a strong, leak-free joint.

D.Inspection, cleaning, priming

Visually inspect the inside of the pipe and fitting sockets and remove all dirt, grease or moisture with a clean dry rag. If wiping fails to clean the surfaces, a chemical cleaner must be used. Check for possible damage such as splits or cracks and replace if necessary.

Depth-of-entry

Marking the depth of entry is a way to check if the pipe has reached the bottom of the fitting socket in Step F. Measure the fitting depth and mark this distance on the pipe O.D. You may want to add several inches to the distance and make a second mark as the primer and cement will most likely destroy your first one.

Apply primer to the surface of the pipe and fitting socket with a natural bristle brush. This process softens and prepares the PVC or CPVC for the solvent cementing step. Move quickly and without hesitation to the cementing procedure while the surfaces are still wet with primer.

E.Application of solvent cement

Applythesolventcement evenly andquicklyaround the outside ofthe pipe at a width a little greater than the depth of the fitting socket.

Apply a light coat of cement evenly around the inside of the fitting socket. Avoid puddling.

Apply a second coat of cement to the pipe end.

STEPE

F. Joint assembly

Working quickly, insert the pipe into the fitting socket bottom and give the pipe or fitting a 1/4 turn to evenly distribute the cement. Do not continue to rotate the pipe after it has hit the bottom of the fitting socket. A good joint will have sufficient cement to make a bead all the way around the outside of the fitting hub. The fitting will have a tendency to slide back while the cement is still wet so hold the joint together for about 15 seconds.

STEPF

G. Cleanup and joint movement

Remove all excess cement from around the pipe and fitting with a dry cotton rag. This must be done while the cement is still soft.

The joint should not be disturbed immediately after the cementing procedure, and sufficient time should be allowed for proper curing of the joint. Exact drying time is difficult to predict because it depends on variables such as temperature, humidity and cement integrity. For more specific information, you should contact your solvent cement manufacturer.

STEP G

22

Image 22
Contents Series Six HV640YBVITCGA HV650YBVITCGA HV640HBVITCGA HV650HBVITCGASafe INSTALLATION, USE and Service Important DefinitionsSafety Precautions Table of Contents Attempting to Install or Operate the Water Heater Product SpecificationsPreparing for the Installation Customer ResponsibilitiesAccessories Materials and Basic Tools NeededNatural HOT Surface Igniter & Main Burner Typical InstallationPropane HOT Surface Igniter & Main Burner Mixing Valve Usage Installation Instructions Removing the Old Water HeaterFacts to Consider about the Location Insulation Blankets ALL AIR from Inside Buildings See Water Piping Hotter Water can ScaldTEMPERATURE-PRESSURE Relief Valve Valve and Pipe Insulation if suppliedGAS Piping with Flexibleconnector GAS PipingSediment Traps Blower Assembly InstallationSequenceofinstallation Filling the Water HeaterVent Connections to Blower Assembly Venting and InstallationCondensation Maximum Vent LengthsVent Terminal Installation VentingVertical Vent Through Roof Vertical Vent RestrictionsVent Pipe Preparation Recommended BRUSH* Size for Primer Cement ApplicationsStepf StepbStepe Step GDo not try to light the burner by hand PowerbeforeservicingOperating Instructions What to do if YOU Smell GASTemperature Regulation Temperature Setting Burns on Adult SkinStart UP Conditions For Your InformationOperational Conditions Venting System Inspection Service and AdjustmentBurner Cleaning Burner Operation and InspectionService TEMPERATURE-PRESSURE Relief Valve OperationDrain Valve Washer Replacement Anode ROD Inspection DrainingLeakage Checkpoints Troubleshooting Guidelines Water Heater ControlTroubleshooting Guidelines Maytag GAS Water Heater Repair Parts ListBurner Assembly Outer Door Alternate HV640YBVITCGALimited Tank Warranty Against Leaks Full ONE Year WarrantyLimited Parts Warranty To Receive Warranty Service