VENT PIPE PREPARATION

1.INITIALPREPARATION

A.Make sure the solvent cement you are planning to use is designed for the specific application you are attempting.

B.Know the physical and chemical characteristics and limitations of the PVC and CPVC piping materials that you are about to use.

C.Know the reputation of your manufacturer and their products.

D.Know your own qualifications or those of your contractor. The solvent welding technique of joining PVC and CPVC pipe is a specialized skill just as any other pipe fitting technique.

E.Closely supervise the installation and inspect the finished job before start-up.

F.Contact the manufacturer, supplier, or competent consulting agency if you have any questions about the application or installation of PVC and CPVC pipe.

G.Take the time and effort to do a professional job. Shortcuts will only cause you problems and delays in start-up. By far, the majority of failures in PVC and CPVC systems are the result of shortcuts and/or improper joining techniques.

2.SELECTION OF MATERIALS

Cutting Device - Saw or Pipe Cutter

Deburring Tool, Knife, File, or Beveling Machine (2" and above)

Brush - Pure Bristle

Rag - Cotton (Not Synthetic)

Primer and Cleaner

• Solvent Cement - PVC for PVC Components and CPVC for CPVC Components

Containers - Metal or Glass to hold Primer and Cement. Select the type of PVC or CPVC materials to be used on the basis of their application with respect to chemical resistance, pressure rating, temperature characteristics, etc.

Insertion Tool - Helpful for larger diameter pipe and fittings 6 inches (15.2 cm) and above.

PRIMER

It is recommended that Tetrahydrofuran (THF) be used to prepare the surfaces of pipe and fittings for solvent welding. Do not use water, rags, gasoline or any other substitutes for cleaning PVC or CPVC surfaces. A chemical cleaner such as MEK may be used.

CEMENT

The cement should be a bodied cement of approximately 500 to 1600 centipoise viscosity containing 10-20% (by weight) virgin PVC material solvated with tetrahydrofuran (THF). Small quantities of dimethyl

formamide (DMF) may be included to act as a retarding agent to extend curing time. Select the proper cement; Schedule 40 cement should be used for Schedule 40 pipe. Never use all-purpose cements, commercial glues and adhesives orABS cement to join PVCorCPVCpipe and fittings.

APPLICATORS

Select a suitable pure bristle type paint brush. Use a proper width brush or roller to apply the primer and cement (see chart below). Speedy application of cement is important due to its fast drying characteristics. IMPORTANT NOTE: A dauber type applicator should only be used on pipe sizes 2" and below. For larger diameter pipe, a brush or roller must be used.

RECOMMENDED BRUSH* SIZE FOR PRIMER

AND CEMENT APPLICATIONS

 

Nominal Pipe

 

Size Brush Width

 

(IPS)

 

(INS.)

 

2

 

1-1/2

 

3

 

1-1/2 - 2-1/2

 

*USE ONLYNATURALBRISTLE

 

3. MAKING THE JOINT

 

A. Cutting

Pipe must be squarely cut to allow for the proper interfacing of the pipe end and the fitting socket bottom. This can be accomplished with a miter box saw or wheel type cutter. Wheel type cutters are not generally recommended for larger diameters since they tend to flare the corner of the pipe end. If this type of cutter is used, the flare on the end must be completely removed.

NOTE: Power saws should be specifically designed to cut plastic pipe.

STEP A

21

Image 21
Contents HV640YBVITCGA HV650YBVITCGA HV640HBVITCGA HV650HBVITCGA Series SixImportant Definitions Safe INSTALLATION, USE and ServiceSafety Precautions Table of Contents Preparing for the Installation Product SpecificationsAttempting to Install or Operate the Water Heater Customer ResponsibilitiesMaterials and Basic Tools Needed AccessoriesTypical Installation Natural HOT Surface Igniter & Main BurnerPropane HOT Surface Igniter & Main Burner Mixing Valve Usage Removing the Old Water Heater Installation InstructionsFacts to Consider about the Location Insulation Blankets ALL AIR from Inside Buildings See Hotter Water can Scald Water PipingValve and Pipe Insulation if supplied TEMPERATURE-PRESSURE Relief ValveGAS Piping GAS Piping with FlexibleconnectorSequenceofinstallation Blower Assembly InstallationSediment Traps Filling the Water HeaterVenting and Installation Vent Connections to Blower AssemblyMaximum Vent Lengths CondensationVenting Vent Terminal InstallationVertical Vent Restrictions Vertical Vent Through RoofRecommended BRUSH* Size for Primer Cement Applications Vent Pipe PreparationStepe StepbStepf Step GOperating Instructions PowerbeforeservicingDo not try to light the burner by hand What to do if YOU Smell GASTemperature Setting Burns on Adult Skin Temperature RegulationFor Your Information Start UP ConditionsOperational Conditions Burner Cleaning Service and AdjustmentVenting System Inspection Burner Operation and InspectionDrain Valve Washer Replacement TEMPERATURE-PRESSURE Relief Valve OperationService Anode ROD Inspection DrainingLeakage Checkpoints Water Heater Control Troubleshooting GuidelinesTroubleshooting Guidelines Burner Assembly Outer Door Alternate Repair Parts ListMaytag GAS Water Heater HV640YBVITCGALimited Parts Warranty Full ONE Year WarrantyLimited Tank Warranty Against Leaks To Receive Warranty Service