Bryant 355CAV installation instructions Combustion AIR Pipe, Unit Corrosion Hazard

Page 32

NOT IN HORIZONTAL SECTION

FURNACE

PIPE DIAMETER

TRANSITION IN

VERTICAL SECTION

A93034

NOTE: Select 1 vent pipe connection and￿ NOTE: Select 1 vent pipe connection and￿

1 combustion-air pipe connection.

1 combustion-air pipe connection.

AIR￿

 

 

 

 

COMBUSTION-￿ FLOW

COMBUSTION-￿

 

 

 

AIR

AIR

VENT

 

 

VENT

 

 

 

VENT

 

 

 

 

 

VENT

 

 

 

 

 

COMBUSTION-￿

 

COMBUSTION-￿

 

 

AIR

AIR￿

AIR

 

 

 

 

 

 

 

FLOW

 

UPFLOW

 

DOWNFLOW

355CAV

Fig. 38 - Combustion Air and Vent Pipe Transition

Location and Elbow Configuration

!CAUTION

UNIT OPERATION HAZARD

Failure to follow this caution may result in intermittent unit operation.

When installing combustion air and vent system of short pipe length, the smallest allowable pipe diameter must be used.

!CAUTION

UNIT CORROSION HAZARD

Failure to follow this caution may result in unit component damage.

Excessive exposure to contaminated combustion air may result in safety and performance related problems. Combustion air must not be taken from inside structure because that air is frequently contaminated by halogens, which include fluorides, chlorides, bromides, and iodides. These elements are found in aerosols, detergents, bleaches, cleaning solvents, salts, air fresheners, adhesives, paint, and other household products. Locate combustion-air inlet as far as possible from swimming pool and swimming pool pump house.

EXAMPLE: This 80,000 BTUH furnace located in Indianapolis, elevation 650 ft above sea level, could be installed as a direct vent/2-pipe system that requires 3 elbows and 17 ft of vent pipe, along with 5 elbows and 16 ft of combustion-air pipe. Table 7 indicates this application would allow a 1-1/2-in. diameter vent pipe, but require a 2-in. diameter combustion air pipe. According to Table 7, 1-1/2-in. diameter pipe is good for 20 ft with 3 elbows, but only 10 ft with 5 elbows. Therefore, 2-in. diameter pipe must be used for both vent and combustion-air pipes since the largest required diameter must always be used for both pipes. If the same installation was made in Albuquerque, elevation 5250 ft above sea level, installation would require 2- in. diameter vent pipe and combustion-air pipe. At 5001 to 6000-ft elevation, 1-1/2-in. pipe is not allowed with 5 elbows, but 2-in. pipe is good for 68 ft with 5 elbows are required.

COMBUSTION AIR PIPE

General

Furnace combustion-air connection must be attached as shown in Fig. 39. Combustion-air intake housing plug may need to be relocated in some applications.

 

 

COMBUSTION-￿

COMBUSTION-￿

AIR

 

AIR

VENT

VENT

 

AIR￿

AIR￿

FLOW

FLOW

HORIZONTAL-LEFT DISCHARGE

HORIZONTAL-RIGHT DISCHARGE

A96187

Fig. 39 - Combustion Air and Vent Pipe Connections

NOTE: All pipe joints must be cemented except attachment of combustion-air pipe to inlet housing connection, since it may be necessary to remove pipe for servicing.

NOTE: A 2-in. diameter pipe must be used within the furnace casing. Make all pipe diameter transitions outside furnace casing.

Attachment of Combustion Air Pipe

NOTE: Combustion air pipe system has the same diameter and same length as the vent pipe as mentioned in section “Combustion- -Air and Vent Pipe Diameter.”

1.Determine location of combustion-air intake pipe connection to combustion-air intake housing as shown in Fig. 39 for application.

2.Verify combustion-air intake housing plug fitting is installed in appropriate unused intake housing connection.

3.Install combustion-air pipe grommet (factory-supplied in loose parts bag) into selected furnace casing combustionair pipe hole.

4.Determine the number of combustion air disk halves to be installed in the combustion air intake housing. Insert perforated disk half or assembly (factory supplied in loose parts bag) in intake housing where combustion-air intake pipe will be connected.

5.Insert assembled combustion air inlet pipe into intake housing as shown in Fig. 39.

NOTE: Do not cement combustion air intake pipe permanently to combustion air intake housing since it may be necessary to remove pipe for service of igniter or flame sensor.

6.Drill a 1/8-in. hole in 2-in, combustion air pipe using the hole in intake housing as a guide.

7.Install a field-supplied No. 6 or No. 8 sheet metal screw into combustion air pipe.

32

Image 32
Contents Installation Instructions Table of ContentsRequired Notice for Massachusetts Installations Safety Considerations CUT HazardDimensions In. / mm Dimensional DrawingInstallation Codes and Standards Electrostatic Discharge ESD Precautions IntroductionApplications Upflow ApplicationCondensate Trap Tubing Alternate Upflow Orientation Condensate Trap Alternate Upflow OrientationCarbon Monoxide Poisoning Hazard Condensate Trap Freeze Protection Upper Inducer Housing Drain ConnectionCondensate Trap Field Drain Attachment Downflow Applications Condensate Trap LocationHorizontal Left Tube Configuration Horizontal Left SUPPLY-AIR Discharge ApplicationsProperty Damage Manual Shutoff GAS Valve Sediment Trapcondensate TrapUnit Operation Hazard Horizontal Right SUPPLY-AIR Discharge ApplicationsConstruct a Working Platform Location Condenste Trap Field Drain AttachmentProhibit Installation on Back Fire or Death HazardUnit MAY not Operate Hazard InstallationFIRE, EXPLOSION, Injury or Death Hazard Furnace, Plenum, and Coil Assembly or Coil Box Locations Reqd PER ROD AIR Ducts Unit MAY not Operate Fire HazardFIRE, Carbon Monoxide and Poisoning Hazard Fire or Explosion Hazard Bottom Closure PanelGas Piping Removing Bottom Closure Panel Electrical Shock Hazard WiringMaximum Capacity of Pipe Disconnect Switch and Furnace Electrical Shock and Fire HazardFire or Electrical Shock Hazard Factory Installed J-Box LocationAccessories AIR for Combustion and Ventilation Fire and Explosion HazardAstm Material Pipe FittingsDescription CementFurnace Control Direct Vent Termination Clearance Ventilated Combustion Air Vent Termination Clearance Vent Pipe Termination for Ventilated Combustion Air System Combustion AIR Pipe Unit Corrosion HazardAttachment of Combustion Air Intake Housing Plug Fitting Combustion Air Termination Ventilated Combustion Air OptionVent Pipe Combustion Air Termination-Direct Vent / 2-Pipe SystemCarbon Monoxide Poisoning Property Damage Hazard Attachment of Vent Pipe304.8mm minimum 76.2mm minimum Vent Termination Extended Exposed Sidewall PipesVent Termination Kit Direct Vent/2-Pipe System Only Two-Pipe Termination Kit Direct Vent/2-Pipe System Only042060 Maximum Allowable Pipe Length Ft / M BtuhUnit Size Condensate Drain Personal Injury HazardSTART-UP, Adjustment and Safety Check Air Conditioning A/C Setup SwitchesContinuous Fan CF Setup Switches Additional Setup Switches SW4Example of Setup Switch in Off Position Prime Condensate Trap with WaterWiring Diagram Inducer Housing Drain Tube Furnace Setup Switch DescriptionSequence of Operation Purge Gas LinesTwo-Stage Thermostat and Two-Stage Low / High Heating Thermidistat Mode See -55 for thermostat connectionsSuper Dehumidify Mode Continuous Blower ModeContinuous Blower Speed Selection from Thermostat Heat PumpStep-Modulating Furnace with Single-Speed Air Conditioning Pump Furnace and Two-Speed Air Conditioner Furnace and Two-Speed Heat PumpSet Gas Input Rate Redundant Automatic Gas ValveBurner Orifice A07253 A07254 Altitude Derate Multiplier for U.S.A Burner FlameSet Thermostat Heat Anticipator Set Temperature RiseGas Rate cu Ft/Hr Checklist Check Safety ControlsCheck Pressure Switches Check Primary Limit ControlChecklist Installation Combustion and Vent Piping
Related manuals
Manual 14 pages 23.93 Kb Manual 62 pages 7.79 Kb

355CAV specifications

The Bryant 355CAV is a state-of-the-art automated vertical machining center designed to enhance precision and efficiency in the manufacturing sector. Renowned for its robust construction, this machine is engineered to handle a broad spectrum of machining tasks, making it suitable for both small and large-scale production environments.

One of the standout features of the Bryant 355CAV is its advanced CNC control system, which provides users with exceptional ease of use. The intuitive user interface allows operators to program complex machining operations with minimal effort, significantly reducing setup times. The machine's high-speed spindle achieves impressive rotational speeds, which allows for quick material removal, ultimately optimizing productivity and throughput.

The Bryant 355CAV exhibits superior rigidity and stability due to its solid cast iron frame and carefully designed structural components. This construction minimizes vibrations during machining, ensuring that even the most intricate parts are produced with high accuracy. The machine's precision ground linear guideways further enhance its performance by providing smooth motion and high load capacity.

Equipped with a large work envelope, the Bryant 355CAV enables manufacturers to accommodate various part sizes and geometries. Additionally, its automatic tool changers can hold a variety of tools, thus facilitating quick transitions between different machining operations without requiring manual intervention. This flexibility is essential for meeting the diverse needs of modern manufacturing.

Another notable characteristic of the Bryant 355CAV is its energy-efficient design. It integrates modern technologies aimed at reducing power consumption while maintaining optimum performance. This environmentally conscious approach not only cuts operational costs but also aligns with the growing demand for sustainable manufacturing practices.

Moreover, the Bryant 355CAV features advanced monitoring capabilities, allowing operators to track machine performance in real time. Data analytics from these systems can be utilized to improve operational efficiency, reduce downtime, and enhance predictive maintenance protocols.

In summary, the Bryant 355CAV is a versatile, high-performance machining center that showcases cutting-edge features and technologies. Its combination of user-friendly controls, sturdy construction, energy efficiency, and advanced monitoring positions it as a vital asset for manufacturers aiming to elevate their productivity and precision in an increasingly competitive landscape.