Desa (V)T36EPA installation manual High Altitude Installation, Vertical Venting

Page 16

Venting Installation

instructions

Continued

Note: Install restrictor into inner collar of fireplace as shown.

Vertical Venting

V = 40' max.

Note: Install restrictor into inner collar of fireplace as shown.

45° Elbow

45° Elbow

Venting with Two 90° Elbows

Vertical (V1)

Horizontal (H)

5' min.

6' max.

6' min.

12' max.

7' min.

18' max.

8' min.

20' max.

Note: Vertical (V1) + Vertical (V2) = 40' max.

Figure 23 - Vertical Venting

Configuration Using Two 90° Elbows

(Vertical Round High Wind Termination

Shown)

Figure 24 - Vertical Venting

Configuration With No Horizontal Run

(Vertical Round High Wind Termination

Shown)

High Altitude Installation

Your DESAdirect-vent fireplace has been tested and approved for elevations from 0-2,000 feet (USA) and elevations from 0-4,500 feet (Canada).

When installing this fireplace at an elevation above 2,000 feet (in the USA), you may need to decrease the input rating by changing the existing burner orifice to a smaller size. Reduce input 4% for each 1,000 feet above sea level. Check with your local gas company for proper orifice size identification.

When installing this fireplace at an elevation above 4,500 feet (in Canada), check with local authorities.

Consult your local gas company to help determine the proper orifice for your location.

For assistance with any high altitude installation, contact DESA’s Customer Service Department at 1-866-672-6040.

16

www.desatech.com

111251-01E

Image 16
Contents What to do if YOU Smell GAS Table of Contents Safety InformationSafety Information Product Features Local CodesProduct Identification High traffic areasLocation and space requirements Pre-Installation PreparationProper clearances must be maintained Clearances Framing and finishingFront Top of Standoffs Vent See venting Venting clearancesLocation of Termination Cap Balcony with Perpendicular Side WallVenting Installation Instructions Installation PrecautionsInstallation Planning Installing Horizontal Vent Cap Noncombustible Exterior Ground Floor Installation 32 minSnorkel Termination Installation Recommended Applications Corner ground floor installationHorizontal System Installation Using TWO 90 Elbows Flat Ceiling Installation Installation for vertical terminationConnect a section of pipe and extend up through the hole Twist-lock the vent cap onto the last section of vent pipe High Altitude Installation Vertical VentingDesa Venting Accessories Desa ElbowsDesa Terminations Number DescriptionFireplace Installation Installing optional blower accessoriesModel BK Installation Check GAS TypeModel BKT Installation Plug in blower power cord to duplex outletBlower Wiring Diagram Installing Gas Piping to Fireplace LocationInstallation Items Needed Connecting Fireplace to GAS Supply Checking GAS ConnectionsPressure Testing Fireplace Gas Connections Test Pressures Equal To or Less Than Psig 3.5 kPaCleaning Glass Door Removing/Replacing Glass DoorRemoving Louver Panels Removing Glass DoorInstalling logs, lava rock and glowing embers Close top and bottom louversInstalling Log No Wall Switch Installation Optional Remote control Installation model WRCOpen lower louver panel of firebox Pilot Gas Wiring DiagramLine Operating Fireplace For your safety Read before lightingLighting Instructions Inspecting Burners To Turn OFF GAS To ApplianceOptional Remote Operation Burner Flame PatternCleaning Maintenance Glass DoorPilot and burners LogsCleaning and Maintenance TroubleshootingObserved Problem Possible Cause Remedy Venting systemGas leak. See Warning Tery power is low Remote Improper log placementClean out air holes at burner Glass soots Flame impingement on logsIllustrated Parts Breakdown Parts List Illustrated Parts Breakdown KEY Description Replacement Parts Service HintsTechnical Service SpecificationsAccessories Keep this Warranty Warranty InformationLimited Warranty DIRECT-VENT Fireplace