Vermont Casting DVHVAC36 manual Typical Ceil

Page 18

DVHVAC36

 

 

Max 8'

 

 

(2.4 m)

 

 

45°

Typical Ceil-

 

40'

ing Support

 

Application

 

(12 m)

 

 

Max 8'

 

 

(2.4 m)

 

 

45°

 

 

 

Typcal Roof

 

 

Support Ap-

 

 

plication

Fig. 31

Typical vertical roof application.

 

5.Place fireplace into position.

6.Place firestop(s) #7DVFS or attic insulation shield #7DVAIS into position and secure. (Fig. 32)

7.Install roof support (Fig. 33) and roof flashing, mak- ing sure upper flange is below the shingles. (Fig. 33)

8.Install appropriate pipe sections until the venting is above the flashing. (Fig. 33)

9.Install storm collar and seal around pipe.

10.Add additional vent lengths for proper height. (Fig. 34)

11.Apply high temperature sealant to 4" and 7" collars of vertical vent termination and install.

If there is a room above ceiling level, firestop spacers must be installed on both the bottom and the top side of the ceiling joists. If an attic is above ceiling level a 7DVAIS (Attic Insulation Shield) must be installed. (Fig. 32)

The enlarged ends of the vent section al- ways face downward. (Fig. 33)

Attic Insulation

Shield

Joist

 

 

11"

 

Ceiling In-

11"

Upper Floor

 

 

 

stallation

 

 

 

 

 

Joist

 

 

 

Firestop Spacer

 

 

Nails (4)

CFM100

 

 

 

Fig. 32 Place firestop spacer(s) and secure.

3 #5 Sheet Metal

Screws per Joint

Sealant

Storm Collar

TWL101a

Fig. 33 Roof flashing.

Vent Termination

 

2'

Storm Collar

 

(610mm)

 

Min.

 

 

Roof Support

Roof Flashing

 

 

40'

Attic Insulation

 

Shield

 

(12.m)

Attic Insula-

 

 

tion

 

 

Joists

 

 

 

Joists

FP1022

Fig. 34 Typical straight-up installation.

18

10001195

Image 18
Contents Rear Direct Vent Model DVHVAC36 Table of Contents Installation & Operating Instructions Please Review the Following CarefullyFireplace Dimensions DVHVAC36Unit Assembly Locating Your Gas FireplaceClearance to Combustibles Mantel Framing and FinishingSupply Air Duct Systems Return Air PlenumHearth Gas Line InstallationFinal Finishing Gas Inlet & Manifold PressuresTypical gas supply installation Electrical SpecificationsElectrical General VentingLocation of Vent Termination Canadian Installations1 US Installations2 General Venting Information Termination LocationGeneral Information Assembling Vent Pipes Canadian InstallationsUSA Installations Twist Lock PipesRear Wall Installations How to Use the Vent GraphCorner Installation Sidewall Venting GraphVertical Sidewall Applications Locate vent opening on wall+ B = 17 5.2m Max Vertical Sidewall Installations Zero clearance sleeve is only required for combustible wallsBelow Grade Installation Always install Horizontal vent Ing on a level PlaneVertical Through-the-Roof Installation Vertical Through-the-Roof ApplicationsTypical Ceil Twist Lock Venting Components Operating Instructions Flame Characteristics Setting Temperature RiseFlame Adjustment Lava RockInspecting the Venting/Heating Exchange System Ceramic Refractory InstallationInspecting the Venting System Mortar lines must be alignedLighting & Operating Instructions To Turn Off Gas To HeaterWhat to do if YOU Smell GAS Troubleshooting the Gas Control System SIT Nova 825 Millivolt ValveMaintenance Cleaning the Standing Pilot Control SystemDVHVAC36 DescriptionDVHVAC36 Do not remove existing window frame as- sembly Optional AccessoriesDecorative Bay Window Remove all plastic from brass trimsDVHVAC36 Page Limited Lifetime Warranty Product Covered by this WarrantyEfficiency Ratings AFUE%