Weil-McLain CGS-4E Boiler isolation balancing valves Flow/check valve, Relief valve, Fill valve

Page 17

GOLD CGs-4E Gas-Fired Water Boiler — Boiler Manual

3c Water piping — multiple zones (continued)

Figure 6

Zoning with circulators

Figure 7

Zoning with zone valves

 

— return water 130°F or higher.

 

— return water 130°F or higher.

1Boiler isolation (balancing) valves

2Flow/check valve

3System or zone circulator

5Zone valve

6Drain valve

9Relief valve

10Automatic air vent (with diaphragm-type expansion tank), or connect to tank fitting (closed-type expansion tank). DO NOT use an automatic air vent when using closed-type expansion tank. It would allow air to leave the system, causing waterlogging of the expansion tank.

11Fill valve

12Diaphragm-type or bladder-type expansion tank, if used (For closed- type expansion tank, pipe from top of air separator to tank fitting as in Figure 5, page 15.)

13Air separator and automatic vent, if used (Note that the fill valve must always be connected to the expansion tank, regardless of location of expansion tank circulator or air separator.

For systems with possible low return-water temperature (such as converted gravity systems, radiant heating systems and heat pump systems), refer to the special piping suggestions of Figures 8 - 12, as applies. Failure to prevent sustained low return water temperature to the boiler could cause corrosion of the boiler sections, resulting in severe personal injury, death or substantial property damage.

Part number 550-110-282/1108

17

Image 17
Contents GOLDCGs-4E How it works Gold CGs-4EGas-Fired Induced-Draft Water Boiler Contents User InstallerPlease read before proceeding Before locating the boiler, check the following 1a Prepare boiler location codes & checklistInstallations must follow these codes 1b Prepare boiler location clearances 1c Prepare boiler location vent system When removing boiler from an existing common vent systemCGs-4E special vent system Vent systemAreas likely to have contaminants 1d Prepare boiler location contaminationProducts to avoid Combustion air requirements 1e Prepare boiler location air openingsSpecial considerations Sizing air openingsSizing air openings for CGs-4E installations Orifice replacement procedure 2a Prepare boiler placement & setupPlace boiler/crate near position Inspect orifices and burnersHydrostatic pressure test 2b Prepare boiler pressure testDrain and remove fittings Prepare boiler for test3a Water piping general information 3b Water piping single-zone system Install an automatic air vent in air vent tapping as shownPiping multiple zones 3c Water piping multiple zonesSystem or zone circulator Zone valve Drain valve Boiler isolation balancing valves Flow/check valveRelief valve Fill valveValve adjustment Figures 8 and 9 only Temperature gauges3d Piping low temp systems Primary/secondary preferred bypass piping methodBoiler isolation balancing valves Blend temperature gaugeBOILER-bypass piping method Valve adjustmentFigures 8 SYSTEM-bypass piping method Boiler 3e Water piping refrigeration systemsPrevent chilled water from entering Combustion air openings Combustion air quality Venting and combustion airVent system Gas piping Connecting gas supply piping to boilerNatural Gas Propane GasElectrical installation must comply with Field wiringWiring connections Thermostat7a Start-up preparation Freeze protection when usedDetermine if water treatment is needed Check for gas leaksInspect system water piping Inspect base insulation 7b Start-up operate boilerFinal check before starting boiler Start the boilerMain burner flame Figure Check burner flamesPilot burner flame Figure 7c Start-up if boiler doesn’t start If none of the above corrects the problem, refer toCheck for Gas not turned on at meter or boiler?Installation and service certificate Check-out procedure checklistBoiler is now in the off cycle 9a Operation sequenceSequence returns to step Operation sequence Wiring diagram 9b Operation wiring diagrams9c Operating instructions CGs-4E CMR 5.082a 1 through Addendum Instruction for Commonwealth of MassachusettsExemptions The following equipment is exempt from CMR 5.082a1 through10a Service and maintenance schedule 10b Service & maintenance annual start-up Burners, base and inlet air box With boiler power off, place a few drops of S.A.ECondensate drain system Inducer motor10b Service & maint. annual start-up Relief valve, typical Boiler relief valveReview with owner Clean between sections with wire flue brushShut down boiler Place newspapers in base of boiler to collect sootBefore troubleshooting 11a Troubleshooting procedureCheck the following Can resultAir pressure switch 11b Troubleshooting air pressure switchCheck pressure switch setting Troubleshooting air pressure readingControl indicator lights Lockout modes 11c Troubleshooting control moduleControl indicator lights NON-LOCKOUT modes Troubleshooting the control moduleControl module connections Chart 1 Troubleshooting Power light status 11d Troubleshooting control module lightsChart 2 Tstat Circ & Power lights flashing Chart 3 Press Switch & Power lights flashing Chart 4 Flame & Power lights flashing Does blower motor operate? Item 8 , Verify Sequence of operation, , Weil-McLain part numbers are found in Weil-McLain Boilers 12a Replacement partsSection assembly Base Jacket Trim Controls Weil-McLain part number 12b Replacement parts section assemblyBase assembly 12c Replacement parts baseDescription Weil-McLain Part number Jacket assembly 12d Replacement parts jacketBoiler Fittings shown are factory-installed on boiler 12e Replacement parts trimPropane gas components 12f Replacement parts controlsDimensional drawing 13a DimensionsTested for 50 psi working pressure 13b RatingsEye Irrigate immediately Breathing Fresh air Handling ceramic fiber and fiberglass materialsThis type of respirator is based on